Mahanoy Township

Anti-Data Center Policies

Schuylkill County’s measure gives local officials a protected period to fix zoning gaps, which can delay developers challenging existing rules but does not prohibit every data-center project.

Rating and summary from Schuylkill County as there are no scored current or future laws outside temporary restrictions for Mahanoy Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Mahanoy Township
The township secretary sent the October 2026 revised draft on October 21, 2026 and said another public hearing is set for November 4, 2026, with a decision expected on November 10, 2026.Mahanoy Township, Schuylkill County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.

Restrictions & requirementsHide restrictions & requirements28
  • Conditional use by the Supervisors; approval does not lapse, § 407.3 and § 903.4.C

  • 100-ft height including roof equipment, § 407.3.f

  • Site constraints report and state permits only; no impact assessment, § 407.3

  • Development under an approved campus master plan needs no new conditional use, § 903.4.D

  • 67 dBA by day and 57 dBA at night, § 407.3.J

  • Section 407.3.J.1 of the October draft requires preliminary, interim, and as-built sound studies using ANSI S1.4-2014 sound level meters, with the as-built study six months after the certificate of occupancy, but the limits apply to normal operations and no study is required at full operating load.

  • Generator testing schedule disclosed only; no limits, § 407.3 checklist J

  • Vibration study showing none measurable past the property line, § 407.3.J.3.

  • Public water required and wells barred as the primary cooling source; no pump tests, § 407.3.i and I.iii

  • Closed-loop required; alternatives only if they use no more water and less energy, § 407.3.I.

  • Drought response plan and daily demand disclosed; no cap or ongoing reporting, § 407.3

  • Wastewater statement on cooling water treatment and will-serve letters, § 407.3

  • State and federal generator permits and emissions calculations required, § 407.3

  • Removal of servers and lawful disposal or recycling of batteries and refrigerants, § 407.3 decommissioning.

  • Utility capacity confirmation before a building permit; no electrical inspection, § 407.3

  • Energy use plan required, § 407.3

  • Substations at the side or rear and screened, and lines of 34.5 kV or less buried, § 407.3.C

  • Section 407.3 of the October draft requires a Power and Utility Demand Statement with the conditional use application identifying transmission or distribution upgrades and substations (submission item 7), and requires proof that the data center or utility pays for all new power infrastructure upgrades, but does not require the estimated cost, the tariff terms, or an executed service agreement.

  • 200-ft buffer yards with landscaping, berms, or walls, § 407.3.

  • Equipment screened by walls or enclosures; no 12-ft standard, § 407.3.D

  • Elevations and renderings required, § 407.3.A.v

  • Containment, spill, and hazardous materials procedures disclosed; no storage setback, § 407.3 checklist J

  • Section 407.3 of the October draft requires a traffic impact study including construction routing with every conditional use application (submission item 18), but does not set a study area reaching the nearest arterial or interchange the trucks will use.

  • Construction plan with hours and haul routes; no required road bond, § 407.3

  • Security of 110%, but up to three years of marketing and 18 months to decommission, § 407.3

  • As-built sound study after opening, § 407.3.J.1

  • $1,000 per day penalty for noise violations, § 407.3.J.1.

  • Section 903.4 of the October draft makes the applicant responsible for all professional, engineering, legal, and consultant review fees incurred in reviewing the Data Center Land Development Plan, backed by a $20,000 replenishing review escrow.

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the I-Manufacturing District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data