Madison Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Madison Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Madison TownshipProposed Ordinance No. 2026-0714-001, in a draft dated July 9, 2026, was authorized for advertising by the Board of Supervisors on July 14, 2026, and no hearing date or record of adoption was found as of October 27, 2026.Madison Township, Columbia County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places, noise limits and sound testing and money set aside for eventual removal. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements36
Township has no zoning; no district limits, § 2
Land development approval by the Supervisors; no conditional use hearing or special exception, § 2.C
Environmental Impact Assessment and PNDI review required, § 3.A(12)(d) and (f)
Section 3.A(17) requires separate approval for any expansion, intensification, change in capacity or cooling technology, increase in water or energy demand, or added accessory infrastructure, but it does not exempt like-for-like replacement.
60 dBA day and 55 dBA night at the property line, 45 dBA at night at Sensitive Receptor property lines, § 3.A(6)(a)
Ambient noise standard applies only to a request to reduce the setback, § 3.A(5)(a)(iii)
Applicant must use the latest technology to limit low-frequency noise; no dBC limit or study, § 3.A(6)(a)
Section 3.A(6)(a)(i) to (iii) requires preliminary, interim, and as-built sound studies using ANSI S1.4 meters, with the as-built study six months after occupancy, but the as-built study is not required at full operating load.
Generator testing permitted as required by industry standards, with no time or hours limits, § 3.A(6)(b)
Vibration study showing no perceptible vibration beyond the property line, § 3.A(7)(c).
Water feasibility study for nonpublic sources and efforts to use existing waterlines before aquifer withdrawals; no pump tests, § 3.A(11)(b) and (g)
Best available closed-loop systems required only to the extent feasible; evaporative cooling not restricted, § 3.A(11)(h)
Projected water needs disclosed; no cap, reporting, or drought plan, § 3.A(11)(a)
Section 3.A(11)(i) requires the applicant to show that disposal of domestic wastewater and cooling or industrial discharge has been provided and approved by the Sewage Enforcement Officer, the sewer authority, SRBC, or DEP, but Section 2.B only bars construction of improvements until other required approvals are obtained and does not require the approval before the zoning permit.
On-site generators must be Tier 4 or greater; no annual emissions testing or reports, § 4.A(5)
Heat must not be perceptible at the property line and heat impacts assessed; no waste heat reuse review, § 3.A(7)(a) and (12)(f)
Decommissioning plan covers removal of electronic waste, batteries, fuel, and refrigerants, § 3.A(19)(a)-(b).
Interconnection agreement and capacity evidence from the utility, and third-party electrical inspection before occupancy, § 3.A(10)(c)-(d)
On-site energy production encouraged but not required; no energy usage plan, § 3.A(10)(a)
On-site generation serving the data center is a separate use with a separate application; no setbacks stated, § 3.A(10)(b) and § 4.A(2)
Substations counted as Data Center Accessory Uses; burial of lines required only for battery systems, § 1 and § 5.I
Battery storage must meet NFPA 855 with lithium-ion fire suppression, § 5.C(2) and § 5.J(9).
Section 3.A(10)(c) requires an interconnection agreement with the electric service provider and evidence that capacity and infrastructure are sufficient, and makes the applicant pay for needed upgrades, but the upgrades and their cost are not required to be disclosed.
Vegetative buffer around the perimeter within 50 ft of the fence; no minimum width next to homes, § 3.A(13)
Facility screened by year-round vegetative buffering; fences up to 8 ft; no equipment screening height or acoustic screening, § 3.A(13)-(14)
Siting must minimize line-of-sight impacts; no visual study, renderings, or elevations required, § 3.A(3)(b)
Emergency Response Plan accepted by the fire department, radio coverage, and 24-hour contact sign; no annual updates, § 3.A(9)
Types of materials stored must be disclosed; containment required only for battery systems, § 3.A(12)(e)(i)
Third-party electrical inspection before occupancy; annual fire inspections apply only to battery systems, § 3.A(10)(d)
Section 3.A(12)(b) requires a traffic impact study in every case covering construction and operation for roadways, intersections, bridges, and interchanges within one-half mile of the site, but the fixed radius does not necessarily reach the nearest arterial or interchange the trucks will use.
Construction traffic analyzed in the traffic study; no work hours, haul routes, or road bond, § 3.A(12)(b)(iii)
Section 3.A(19)(d) to (g) requires security of 110 percent of decommissioning cost, immediate notice of cessation, and removal within 6 months, but the agreement is not recorded and facilities with an ongoing purpose may remain without a 2-year lawful reuse limit.
Section 3.A(19)(k) and (l) requires decommissioning cost estimates after the first year of operation and every fifth year, and states that the financial security shall be updated every five years.
Section 1 defines a data center to include cryptocurrency mining, blockchain processing, artificial intelligence, and supercomputers, and excludes equipment secondary and customarily incidental to another use, but the exclusion sets no stated size or power limit.
One as-built sound study six months after occupancy, with later studies at Township discretion, § 3.A(6)(a)(iii)
Applicant reimburses Township consultant review fees above $500 and noise expert costs when a violation is found, § 2.C(5) and § 3.A(6)(c)
Sources