Lower Salford Township

Anti-Data Center Policies

Lower Salford Township’s enacted ordinance limits data-center locations through setbacks, minimum site sizes, and eligible-location rules, while retaining an approval route that may significantly narrow feasible projects.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Lower Salford Township
The current rules are in Ordinance No. 2026-07, which the Board of Supervisors adopted on August 5, 2026.Lower Salford Township, Montgomery County — data-center ordinance (No. 2026-07)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and limited eligible locations. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements28
  • Section I of the ordinance maps the Data Center Overlay on the Exhibit A parcels at adoption, Section 164-172.A permits data centers by conditional use within the DCO as delineated on the Zoning Map, and Section 164-174.A.i requires that data centers be located within the DCO.

  • Conditional use, § 164-172; no expiration of approval

  • Environmental impact analysis required, § 164-173.B

  • Section 164-174.I lists increases in electrical demand, water use, accessory uses, footprint, or acreage as triggers for a new conditional use approval, but it does not exempt like-for-like replacement and adds an open-ended catch-all.

  • Section 164-174.D.i.1 sets 40 dBA at night and 45 dBA in the day at the property line, and Section 164-174.D.ix requires ANSI S1.4-2014 meters and criteria accepted by ASA or INCE-USA.

  • 60 dBC day, 50 dBC night, § 164-174.D

  • Section 164-173.B.vii requires a prospective study with the application and Section 164-174.D.ii and iii require interim and as-built studies, with methods stated in Section 164-174.D.ix, but the as-built study six months after occupancy is not required at full operating load.

  • Public water required; no private wells, § 164-174.C.iii

  • Drought response plan and projected use; no cap or reporting, § 164-174.C.iii

  • Public sewer with capacity required, § 164-174.C.iv

  • Fuel types limited; no emission standards

  • Thermal impact mitigation plan; reuse review not confirmed, § 164-173.B.viii

  • Removal and recycling plan for servers, batteries, hazardous materials, § 164-173.B.x, 164-174.G.

  • Utility interconnection agreement showing capacity; no third-party inspection, § 164-174.C.v.

  • Energy usage plan; 10% renewable by purchase agreement, not on site, § 164-174.C.v

  • Substations part of accessory uses; equipment screened, § 164-5, 164-174.B.vii

  • Section 164-173.B.v.8 and 9 require the utility feasibility study to identify proposed utility extensions or upgrades and existing system limitations and required improvements, and Section 164-174.C.vii makes the applicant pay for them.

  • 6 ft berm with 12 ft plantings; width under 100 ft, § 164-174.B.vi

  • Facade offsets, material limits, entrance articulation, § 164-174.B.viii.

  • Equipment fully enclosed or fully screened, acoustic attenuation, 12 ft plantings, § 164-174.B.vi, vii

  • Emergency plan reviewed by fire department; no annual updates, radio, or contacts, § 164-173.B.ix

  • Hazardous materials addressed in waste plan; no storage setbacks, § 164-173.B.x

  • Annual fire safety inspections; no electrical inspection, § 164-173.B.ix

  • Section 164-173.B.iv requires a traffic impact study under Section 142-148 with every conditional use application, but the ordinance does not state that it covers construction traffic or reaches the nearest arterial or interchange.

  • 110% security and 3 month notice; removal within 18 months, § 164-174.G

  • Security is subject to annual increases under the subdivision and land development rules (§ 164-174.G.i), but no updated decommissioning estimate is required after the first year or every five years

  • As-built sound and vibration study 6 months after occupancy, with further monitoring only on Township request up to every 6 months (§ 164-174.D)

  • Public meeting before Planning Commission and project website, § 164-173.B

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Data Center Overlay District on Wambold Road

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data