Lower Nazareth Township’s enacted rules require setbacks from protected places, minimum site sizes, and cooling and water-use limits. Data centers can still be approved, but these restrictions narrow where and how they can operate.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Lower Nazareth TownshipThe current rules are in Ordinance No. 261-05-26, which the Board of Supervisors adopted on May 27, 2026.Lower Nazareth Township, Northampton County — data-center ordinance (No. 261-05-26)
What this means
The measure imposes setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements18
Single 55 dBA hourly average at the property line, § 702.32.I.1
Section 702.32.I.2 requires preliminary, interim, as-built, and post-construction sound studies by a Board-approved noise engineer, but it names no measurement standard or method and does not require any study at full operating load.
Public water and sewer required and on-lot wells barred, § 702.32.J.1
Closed-loop water system required; evaporative cooling not restricted, § 702.32.J.2
Report on greywater discharge with the application, § 702.32.J.3
Utility certification of capacity required; no electrical inspection, § 702.32.K.1.
On-site generation treated as an accessory use with its own approval, § 702.32.K.2
Substations 300 ft from homes and screened; lines not buried, § 702.32.K.3
Only rate impacts must be noted, § 702.32.K.1
150-ft buffer yard with a 12-ft planted screen, § 702.32.H.
Full cutoff fixtures and 0.1 footcandle limit at homes; light past the property line not barred, § 702.32.L
All rooftop and ground equipment fully screened and placed to shield sound, with a 12-ft planted screen, § 702.32.I.2.e and f and H
Plan accepted by the fire department with annual inspections; no annual update, radio coverage, or posted contacts, § 702.32.N.1
Plan must ensure responder training; no funding, § 702.32.N.1[d]
Annual fire safety inspections; no electrical inspection, § 702.32.N.1[e]
Post-construction sound and vibration studies, then on request, § 702.32.I
Section 702.32.I.2.g provides that the certificate of occupancy shall be revoked if a noise violation is not remedied within 30 days, but no notice and hearing is required and Sections 616.1 and 617.2 of the MPC are not cited.
Applicant pays for its own studies only, § 702.32.I.2.g
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the TD-11 district
Sources