Lower Macungie Township’s enacted ordinance requires data centers to be set back from homes and other protected places. Approval remains possible, but siting and operating limits substantially narrow where projects can proceed.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Lower Macungie TownshipThe current rules are in Ordinance 2026-02, which the Board of Commissioners adopted on May 21, 2026.Lower Macungie Township, Lehigh County — data-center ordinance (No. 2026-02)
What this means
The measure imposes setbacks from homes or other protected places. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements20
Conditional use with Commissioners hearing, Section 27-2403; no approval expiration
Section 27-2406.PP(5) bars any data center within 1,000 feet of any residence, school, place of worship, life care facility, or day care, measured from property line to property line.
Environmental impact study required, Section 27-2406.PP(3)
Nuisance standard at 500 ft; no decibel limit, Section 27-2406.PP(9)
Sound study with application and quarterly readings after opening; no building permit study
Public water required with will-serve letter; no hydrogeologic study, Section 27-2406.PP(7)
Closed-loop cooling required; evaporative cooling not restricted, Section 27-2406.PP(11)
Annual water use reporting; no drought plan, Section 27-2406.PP(15)
Public sewer required and EDUs disclosed; no cooling discharge plan
Stormwater controls described in environmental impact study
Generator emissions data disclosed only
Will-serve letter from power company with application; no third-party inspection.
International Fire Code compliance report, Section 27-2406.PP(12)
50-ft Class C buffer yard, Section 27-2406.PP(1)
Screening and security per Township Design Guidelines
Data centers screened from streets and abutting lots; 10-ft berm within 250 ft
Emergency preparedness plan required, Section 27-2406.PP(12)
Risk to first responders addressed generally; no training requirement
Parking study only; no traffic study
Annual reports on water, sewer, power, and quarterly sound readings, Section 27-2406.PP(15)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the I, HE, and ORLIC districts