Lower Frederick Township
Anti-Data Center Policies
Lower Frederick Township’s enacted rules require setbacks, minimum site sizes, noise limits and sound testing for data centers. Projects can still be approved, but fewer sites may qualify.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Lower Frederick TownshipThese standards in Section 170-38.6 and amended Sections 170-83 and 170-84 were set by Ordinance No. 2026-02, which the Board of Supervisors enacted on July 21, 2026, together with new battery facility rules in Section 170-38.7.Lower Frederick Township, Montgomery County — data-center ordinance (No. 2026-02)
What this means
The measure imposes setbacks from homes or other protected places, minimum site-size requirements and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements33
Principal data centers only by conditional use in the LI Limited Industrial District, § 170-38.6.A(1)
500 ft between data center buildings and the curtilage of existing residences, plus 200-ft property line setback, § 170-38.6.A(2) and (6)(c)
40 ft maximum height; exterior mechanical equipment on the ground where feasible but no rooftop height limit, § 170-38.6.A(2) and § 170-84.G(3)
Industrial uses must comply with § 170-41.1 natural resource protection standards, § 170-83.M
Master plan must cover all lots making up the data center site, regulated as one site, § 170-38.6.A(10)(b)
Lots may be added to or removed from the master plan only with Township approval; no phasing rule, § 170-38.6.A(10)(b)
Full spectrum modeling to address low frequency sound and octave band analysis required; no dBC limit, § 170-38.6.A(7)(a)-(b)
Preliminary sound assessment with the conditional use application and as-built assessment 6 months after full operation; none at building permit, § 170-38.6.A(7)(b) and (d)
Section 170-83.N(4)(d) limits backup generator testing to weekdays between 8:00 a.m. and 6:00 p.m. and to one hour per week per unit, with no allowance for longer tests required by code.
Industrial uses must minimize vibration; no numeric standard or study, § 170-83.G
Water-based cooling must use closed-loop or water-efficient technology; evaporative cooling not restricted, § 170-83.N(2)(f)
Water quantity analysis and drought response plan in the feasibility study; no use cap or ongoing reporting, § 170-83.N(2)(c)-(d)
Section 170-83.N(3)(a) requires the applicant to demonstrate that disposal of domestic, cooling, and industrial wastewater has been provided and approved by the Sewage Enforcement Officer or DEP, and Section 170-83.N(3)(b) bars untreated discharge, as performance standards applied to data centers.
Diesel generators must meet EPA Tier 4; no annual emissions testing or reports required, § 170-83.N(4)(d)
Thermal impact plan certified by an engineer, including evaluation of waste heat reuse, § 170-38.6.A(8).
Decommissioning requires disposal of hazardous materials including batteries, fuel, and refrigerants; no server recycling plan, § 170-83.P(5)
Utility certification of available capacity and interconnection documentation required; no third-party electrical inspection, § 170-83.N(4)(b) and § 170-38.6.A(9)(b).
Section 170-38.6.A(9) requires an Energy Usage Plan with the conditional use application stating annual electricity demand, supply sources, and backup power, with rooftop solar on available unshaded roof area, but the plan need not state peak demand by phase or design efficiency.
Generation that supplies the grid is a separate principal use needing its own zoning approval, § 170-83.N(4)(f).
Outdoor ASUs such as substations screened and placed behind the principal building; on-site lines of 34.5 kV and below buried, § 170-84.F(2)-(3) and § 170-83.N(1)(c)
Section 170-83.N(1)(b) requires a utility capacity assessment and requires the applicant to provide at its own expense the system improvements needed where capacity is insufficient, and Section 170-38.6.A(9) requires proof that a utility application was filed, but no upgrade cost estimate, tariff terms, or executed service agreement is required.
Buffer yard under § 170-15 plus an 8-ft berm next to residential districts or uses; width not stated, § 170-38.6.A(6)(a)-(b)
Facades must look like office buildings, with material standards and two design elements every 150 ft, § 170-38.6.A(3) and § 170-84.F(1).
Outdoor ASUs screened by walls, fencing, or evergreens; no height or acoustic standard, § 170-84.F(3) and G(3)
Elevations and renderings of facades visible off site required, § 170-38.6.A(3)
Section 170-83.O requires an Emergency Response Plan approved by the local fire department and emergency management services, recertified annually with an annual site inspection by Township and fire officials, and posted 24-hour contact signage, but the plan is not accepted by a municipal official.
ERP must include procedures and schedules for training local first responders; funding not required, § 170-83.O(2)
ERP covers hazardous material incidents and signage must identify hazardous materials; no storage setbacks or containment, § 170-83.O(1)(h) and (2)
Annual fire safety inspections and annual Township and fire official site inspection; no third-party electrical inspection, § 170-83.O(2) and (5)
Only trip generation figures in the master plan; no traffic impact study, § 170-38.6.A(10)(b)[7]
For facilities over 100,000 sq ft, 110% security and notice after 12 months of cessation, but removal may take up to 18 months after commencement, § 170-83.P(2) and (4)
Township may use the sound security and order shutdown of a noncompliant portion of the data center, § 170-38.6.A(7)(f).
Section 170-38.6.A(7)(d) has the Township obtain the as-built sound assessment from a Township-selected acoustic engineer at the applicant's expense, but the ordinance does not require the applicant to pay for consultant review of its studies in land development review.
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the LI Limited Industrial District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data