Lower Augusta Township
Anti-Data Center Policies
Lower Augusta Township requires data centers to set aside money for eventual removal, meet noise limits and testing rules, and keep specified distances from protected places. Approval remains possible, but these requirements add costs.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Lower Augusta TownshipThe Board of Supervisors adopted these standards as Ordinance No. 2026-2 on October 12, 2026, after a public hearing at the same meeting.Lower Augusta Township, Northumberland County — data-center ordinance (No. 2026-2)
What this means
The measure imposes money set aside for eventual removal, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements37
Conditional use decided by the Supervisors after hearing under Section 708; approval expires if a building or zoning permit is not obtained within 6 months, not tied to start of construction, Section 5H.
300 ft from any Sensitive Receptor property line, which includes residences and parcels where residential use is permitted by right, Section 4C(1)(c)
Environmental Impact Assessment covering riparian buffers, streams, and wetlands; no buffer width, Section 4K
Section 4P requires a new conditional use approval for any expansion, intensification, change in capacity or cooling technology, increase in water or energy demand, or added accessory infrastructure, but it does not exempt like-for-like replacement.
60 dBA day and 55 dBA night at the property line, 45 dBA night at Sensitive Receptor property lines; daytime limit above 50 dBA, Section 4D(1)
Low-frequency noise must be limited through design; no dBC limit or study, Section 4D(1)
Section 4D(1)(a) to (c) require preliminary, interim, and as-built sound studies using ANSI S1.4 meters, with the as-built study six months after occupancy, but the as-built study is not required at full operating load.
Generator testing as required by industry standards is permitted; no hours limit, Section 4D(2)
Vibration study showing no vibration perceptible beyond the property line, Section 4E(3).
Water feasibility study with safe yield and well impacts for nonpublic sources, and existing waterlines must be used first; no bar on wells or pump tests, Section 4J(1)-(2) and (6)
Closed-loop cooling to the extent feasible; evaporative cooling not restricted, Section 4J(7)
Projected water needs disclosed and SRBC approval above thresholds; no cap, reporting, or drought plan, Section 4J(1)-(5)
Section 4J(8) requires the applicant to show that disposal of domestic wastewater and cooling or industrial discharge has been provided and approved by the Sewage Enforcement Officer, Municipal Authority, SRBC, or DEP, but it does not state that the approval must be in hand before the zoning permit.
Stormwater management plan required as part of the impact assessment, Section 4K(5)
Tier 4 or greater generators required; no annual testing or reports, Section 4H(4)
Decommissioning plan covers removal of electronic waste, batteries, and refrigerants; recycling not required, Section 4R(6)-(7)
Utility certification of capacity with the application and third-party electrical inspection before occupancy, Section 4H(3)
On-site power generation is encouraged; no energy usage plan or renewable requirement, Section 4H(1)
Power generation serving the data center is a separate use requiring its own zoning approval, Section 4H(2).
Substations are counted as data center accessory uses; no screening or placement standard, Section 1
Section 4H(3)(a) requires an interconnection agreement with the electric service provider, Section 4H(3)(b) to (d) require evidence that capacity and infrastructure are sufficient, and Section 4H(3)(e) makes the applicant pay for needed upgrades, but the upgrades and their cost are not required to be disclosed.
Vegetative buffer around the entire perimeter within 50 ft of the fence; no minimum width, Section 4L
Buildings must be harmonious with surroundings, with office-like appearance and transitional massing encouraged, Section 4A
Site screened by year-round vegetative buffer; no equipment-specific height or acoustic screening, Section 4L
Siting must minimize line-of-sight impacts, but no elevations or visual study required, Section 4A(2)
Emergency Response Plan accepted by the fire department, radio coverage, and 24-hour contact sign; no annual updates, Section 4G
Types and storage duration of materials disclosed; no storage setbacks or containment, Section 4K(6)(a)
Third-party electrical inspection before occupancy; no annual inspections, Section 4H(3)
Section 4K(2) requires a traffic impact study in every case covering construction and operation for roadways, intersections, bridges, and interchanges within one-half mile of the site, but the fixed radius does not necessarily reach the nearest arterial or interchange the trucks will use.
Traffic analysis covers construction, but no work hours, haul routes, or road bond, Section 4K(2)
Section 4R(2) to (4) require 110 percent financial security, immediate notice of cessation, and removal within 6 months, but the agreement is not recorded and facilities with an ongoing purpose may remain without a 2-year lawful reuse limit.
Section 4R(5) requires decommissioning cost estimates after the first year of operation and every fifth year, and states that the financial security shall be updated every five years.
Section 1 defines a data center to include cryptocurrency mining, blockchain processing, artificial intelligence, and supercomputers, and excludes equipment secondary and customarily incidental to another use, but the exclusion sets no stated size or power limit.
One as-built sound study six months after occupancy, with later studies at the Supervisors' discretion, Section 4D(1)(c)
Sections 4D(1)(c) and 4I(3) and (4) make noise exceedances violations and let the Township rescind or revoke zoning permits for unremediated radiation violations, but no notice and hearing precede revocation and Sections 616.1 and 617.2 of the Municipalities Planning Code are not cited.
Township may retain an independent hydrologist and scientist; costs assigned only for decommissioning estimates and noise experts after a violation, Sections 4D(3), 4J(2), 4K, and 4R(5)
Written statement must name the developer and operator; end user not required, Section 5B(7)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the Commercial (C) District