Lower Allen Township
Neutral Data Center Policies
Lower Allen Township allows data centers in designated districts through a special permit or conditional-use review, providing a path to approval but potentially adding time and uncertainty.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Lower Allen TownshipThe current rules are in Ordinance 2026-04, which the Board of Commissioners enacted on July 13, 2026.Lower Allen Township, Cumberland County — data-center ordinance (No. 2026-04)
What this means
The measure provides a route for data centers through a special permit or conditional-use review in designated districts. That offers legal certainty, but the extra approval step can add time and uncertainty.
Restrictions & requirementsHide restrictions & requirements20
Conditional use; no approval expiration
Section 220-187 sets 45 dBA day and 40 dBA night at perimeter property lines, with pre-construction and post-construction studies sealed by an acoustical engineer at locations the Township identifies, but no metric, meter class, or measurement standard is stated.
60 dBC day and 50 dBC night, § 220-187
Pre-construction and post-occupancy studies, § 220-187
Section 220-208.A(5)(2) limits generator testing to weekdays from 7:00 a.m. to 7:00 p.m., three hours per day, once per week, with no allowance for longer tests required by code.
Sound studies must include vibration levels; no vibration limit, § 220-208.A(5)
Water feasibility study for nonpublic sources; no pump tests or well bar, § 220-208.A(2)
Projected water quantity disclosed, § 220-208.A(2)
Section 220-208.A(3) requires public sewage disposal and requires the applicant to demonstrate that disposal of domestic, cooling, and industrial wastewater has been provided and approved by the governing authority and DEP, with a will-serve letter, as part of the conditional use showing that precedes the zoning permit.
Tier 4 generators, waivable; no annual testing, § 220-208.A(5)
Removal of electronic waste in decommissioning plan, § 220-208.A(4)
Utility capacity letter and interconnection agreement; no electrical inspection, § 220-208.A(1).
Auxiliary power limited to emergency backup, § 220-208.A(5)
Utility equipment co-located and screened, § 220-208.A(1)
Generators enclosed or behind a sound wall; utility boxes screened, § 220-187, § 220-208.A(1)
Emergency plan reviewed by emergency management; 24-hour contact sign; no annual update or radio, § 220-208.A(7)
Security of 100% of net removal cost; no notice or 6-month removal, § 220-208.A(4)
One post-occupancy sound study, § 220-187
Injunctive relief and liens for decommissioning only, § 220-208.A(4)
Decommissioning estimator hired by applicant; no municipal expert review
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the I-1, I-2, and I-3 industrial districts