Loading map…

Lower Allen Township

Neutral Data Center Policies

Lower Allen Township allows data centers in designated districts through a special permit or conditional-use review, providing a path to approval but potentially adding time and uncertainty.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Lower Allen Township
The current rules are in Ordinance 2026-04, which the Board of Commissioners enacted on July 13, 2026.Lower Allen Township, Cumberland County — data-center ordinance (No. 2026-04)

What this means

The measure provides a route for data centers through a special permit or conditional-use review in designated districts. That offers legal certainty, but the extra approval step can add time and uncertainty.

Restrictions & requirementsHide restrictions & requirements20
  • Conditional use; no approval expiration

  • Section 220-187 sets 45 dBA day and 40 dBA night at perimeter property lines, with pre-construction and post-construction studies sealed by an acoustical engineer at locations the Township identifies, but no metric, meter class, or measurement standard is stated.

  • 60 dBC day and 50 dBC night, § 220-187

  • Pre-construction and post-occupancy studies, § 220-187

  • Section 220-208.A(5)(2) limits generator testing to weekdays from 7:00 a.m. to 7:00 p.m., three hours per day, once per week, with no allowance for longer tests required by code.

  • Sound studies must include vibration levels; no vibration limit, § 220-208.A(5)

  • Water feasibility study for nonpublic sources; no pump tests or well bar, § 220-208.A(2)

  • Projected water quantity disclosed, § 220-208.A(2)

  • Section 220-208.A(3) requires public sewage disposal and requires the applicant to demonstrate that disposal of domestic, cooling, and industrial wastewater has been provided and approved by the governing authority and DEP, with a will-serve letter, as part of the conditional use showing that precedes the zoning permit.

  • Tier 4 generators, waivable; no annual testing, § 220-208.A(5)

  • Removal of electronic waste in decommissioning plan, § 220-208.A(4)

  • Utility capacity letter and interconnection agreement; no electrical inspection, § 220-208.A(1).

  • Auxiliary power limited to emergency backup, § 220-208.A(5)

  • Utility equipment co-located and screened, § 220-208.A(1)

  • Generators enclosed or behind a sound wall; utility boxes screened, § 220-187, § 220-208.A(1)

  • Emergency plan reviewed by emergency management; 24-hour contact sign; no annual update or radio, § 220-208.A(7)

  • Security of 100% of net removal cost; no notice or 6-month removal, § 220-208.A(4)

  • One post-occupancy sound study, § 220-187

  • Injunctive relief and liens for decommissioning only, § 220-208.A(4)

  • Decommissioning estimator hired by applicant; no municipal expert review

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the I-1, I-2, and I-3 industrial districts

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data