Locust Township
Anti-Data Center Policies
Locust Township’s enacted ordinance sets noise limits and requires sound testing for data centers, increasing compliance and review costs while still allowing approval.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Locust TownshipThe Board of Supervisors enacted the ordinance on January 5, 2026, and it sets no standards written for data centers, such as setbacks, noise limits, or water rules, leaving conditions to the Zoning Hearing Board case by case.Locust Township, Columbia County — data-center ordinance (Ordinance No. 1-2026, January 5, 2026)
What this means
The measure imposes noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements2
Section 1029.B requires the use to be similar to uses listed for the district but names no district for data centers, so no district limit is stated.
Section 1029.A sends any use neither permitted nor denied, which includes a data center, to the Zoning Hearing Board as a special exception, with Planning Commission comment first (Section 1029.C).
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Special exception by the Zoning Hearing Board for uses the zoning ordinance does not list