Licking Creek Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Licking Creek Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Licking Creek Township
The township secretary provided the unnumbered and undated draft on October 23, 2026, after writing on October 19, 2026 that it was not ready, and no vote or hearing date had been announced.Licking Creek Township, Fulton County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements27
  • Township has no zoning; no district limits

  • Board of Supervisors approval under the SALDO; no conditional use or special exception, Section 7

  • Section 5(c) applies the 1,000-foot setback from existing residential structures and sensitive receptors to principal buildings, Data Center Accessory Use structures, and substations, and the accessory use definition includes generators, cooling towers, and environmental control equipment.

  • 65 ft maximum building height, Section 5(b)

  • Riparian forest buffer of 100 ft on each side, wider on steep slopes and at wetlands, Section 5(y)

  • Single 57 dBA CNEL limit at the property boundary, Section 5 Noise/Vibration (1)

  • Vibration named in a heading but no standard set, Section 5 Noise/Vibration

  • Water feasibility study for nonpublic water, including effects on nearby wells; no pump test, Section 5(s)

  • Open-loop and discharge-based cooling prohibited; evaporative cooling not restricted, Section 5(v)(2)(b)

  • Projected water demands disclosed in the feasibility study; no cap, reporting, or drought plan, Section 5(s)

  • Sewer authority must certify capacity, and discharges are described in the water study, Section 5(s)

  • Stormwater management plan under the Township SALDO, Section 5(u)

  • Tier 4 or greater generators required; no annual emissions testing, Section 5(m)

  • Decommissioning removes hazardous materials, cabling, and electrical components; no recycling plan, Section 6

  • Utility verification of capacity and third-party final electrical inspection, Section 5(i)

  • Renewable energy and LEED only encouraged; no energy usage plan, Section 5(v)-(w)

  • On-site generation permitted subject to environmental, safety, and interconnection standards, Section 5(m)

  • Substations screened and placed to the side or rear; on-site lines of 34.5 kV and below buried, Section 5(l)

  • 30-ft vegetation buffer along the property line, Section 5(o)(3)

  • Low-reflective earth tone colors required; fluorescent and metallic colors prohibited, Section 5(r).

  • Ground equipment behind opaque wall and rooftop equipment screened on four sides; no 12-ft or acoustic standard, Section 5(o)(2)

  • Emergency Response Plan to county EMA and fire departments, in-building radio coverage, 24-hour contact signs; no annual updates, Section 5(n) and (t)

  • Third-party final electrical inspection; no annual fire inspections, Section 5(i)

  • Vehicle trips described in impact analysis; no traffic study, Section 5(q)

  • Security of 100% of net removal cost; no closure notice or removal deadline, Section 6

  • Judgments of up to $500 per day of violation, and permit rescission for radiation violations, Sections 5(z) and 7.

  • Applicant pays Township engineer and Solicitor review fees, Section 7