Lehman Township
Anti-Data Center Policies
Lehman Township’s enacted data-center ordinance limits noise and building height, requires sound testing and setbacks from homes and other protected places, and adds costs; data centers can still be approved.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Lehman TownshipThe Board of Supervisors enacted Ordinance No. 155 of 2025 amending the zoning ordinance on November 20, 2025, and the Pike County Planning and Mapping Director confirmed the adoption by email on October 21, 2026.Lehman Township, Pike County — data-center ordinance (No. 155 of 2025)
What this means
The measure imposes noise limits and sound testing, setbacks from homes or other protected places and building-height limits. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements18
Conditional use; no approval expiration, Section 306
50 dBA 24-hour average; maximums of 65 dBA day and 55 dBA night, Section 402.C.1-2
Noise study for initial operation and expansions, plus as-built study after construction; none at building permit, Section 402.C.4 and C.6
Generator testing weekdays 9 a.m. to 5 p.m. only; no hours cap, Section 402.E.1
Water feasibility study with hydrogeological map and safe yield; no pump test or well bar, Section 402.D
Quarterly water use reporting; no drought plan, Section 402.D.7
Generator emissions must meet federal, state, and local rules, Section 402.E
Utility will-supply letter required; no electrical inspection, Section 402.G.1.
On-site generation limited to outages and to 30 days, Section 402.G.1
Power substations defined and regulated as part of the use with a 300-ft setback, Sections 202 and 402.A.1
Proof of NFPA compliance for generators and fuel storage; no battery rule, Section 402.E
Applicant must show transmission needs will not burden existing supply; no cost assignment, Section 402.G.2
50-ft vegetated buffer along all property lines, Section 402.B
Emergency response plan with 24-hour contacts approved by the Supervisors; no annual update or radio coverage, Section 402.F.1
Applicant must provide and fund responder training and equipment, Section 402.F.
Hazards identified in the response plan and bulk fuel storage rules apply; no spill containment standard, Sections 402.E and F
Quarterly third-party water use reports, Section 402.D.7
Section 402.C.3 has noise compliance determined by a Township-approved acoustical engineer at the applicant's expense and Section 402.D.5 has a Township-chosen firm conduct the water study at the applicant's cost, but no applicant-paid consultant review of studies in land development review is required.
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the I Industrial District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data