Lehman Township
Anti-Data Center Policies
Lehman Township’s enacted rules require setbacks, water-use and cooling controls, and noise limits and testing; data centers can still seek approval, but these restrictions narrow feasible sites and operations.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Lehman TownshipThe rules are in Ordinance No. 072126, which the Board of Supervisors enacted on July 21, 2026, the night of its public hearing, amending the township zoning ordinance.Lehman Township, Luzerne County — data-center ordinance (No. 072126)
What this means
The measure imposes setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements28
Allowed only in the I1 district, so not in agricultural districts; preserved farmland and agricultural security areas not addressed, § 902.15
Section 902.15.A.3 requires data centers and data center accessory uses, which include generators, substations, and cooling equipment, to be set back 1,000 ft from the property line and from any district where residential use is permitted.
Section 902.15.D.4 requires a noise study for proposed expansions and Section 902.15.E.4 projects water demand by phase, but no new approval is required for expansion and no phase states its electrical demand.
Section 902.15.D.1 and D.2 set 45 dBA daytime and 40 dBA nighttime at any property line, and Section 902.15.D.3 and D.6 require leaf-off measurements by a Township-approved acoustical engineer using ANSI S1.4 meters and generally accepted methodology.
Section 902.15.D.6 requires a preliminary study in the conditional use process, an interim study at building permit, and an as-built study six months after occupancy, using ANSI S1.4 meters.
Generator testing hours not addressed; on-site generation limited to outages of no more than 14 days, § 902.15.F.1
Vibration study showing no vibration perceptible beyond the property line, § 902.15.D.8.
Section 902.15.E.2 bars continuous groundwater use for cooling and requires trucked cooling water, and Section 902.15.E.4 requires a feasibility study with drawdown and recovery testing of wells.
Closed-loop, non-evaporative cooling required and open-loop systems prohibited, § 902.15.E.2
Non-cooling well withdrawals capped at 20,000 gallons per day and projected demand disclosed; no drought plan, § 902.15.E.3 and E.4
Section 902.15.E.2 requires DEP approval for disposal of cooling water and Section 902.15.E.6 requires wastewater facilities approved by the SEO or DEP, but neither states that the approval must be in hand before the zoning permit.
Decommissioning plan for equipment removal and disposal or recycling, with batteries and refrigerants disposed under state and federal law; servers not named, § 902.15.J.1 and J.4
Will-supply letter from the public utility required; no third-party electrical inspection, § 902.15.F.1.
Rooftop solar encouraged but not required; no energy usage plan, § 902.15.F.3
On-site energy generation for normal operations prohibited and backup generation limited to 14 days, § 902.15.F.1 and F.2
All new or upgraded power lines serving the data center underground, and power supply equipment near roads and residential districts enclosed or screened; substation placement not addressed, § 902.15.F.1 and C.1
Applicant must show power infrastructure will not place an undue burden on community supply; upgrade costs not assigned, § 902.15.F.1
25-ft planted buffer with native evergreen and canopy trees, § 902.15.B
Facades facing roads or residential uses must change material, height, or depth every 150 ft, and reflective materials are limited, § 902.15.H and I.3.
Equipment near roads, residential districts, and sensitive receptors fully enclosed or screened to reduce sight and noise; no 12-ft height standard, § 902.15.C.1
Emergency Response Plan reviewed and accepted by the fire department; no annual updates, radio coverage, or posted contacts, § 902.15.G.1
Emergency Response Plan must ensure first responders receive system-specific training, § 902.15.G.1.d
Hazardous materials addressed only at decommissioning, § 902.15.J.4
Annual fire safety inspections by a qualified professional, § 902.15.G.1.e
Security covering the full cost of decommissioning, with removal begun within 1 year of cessation and completed within 18 months; no 110% amount, § 902.15.J.2 and J.3
As-built sound study 6 months after occupancy, and the township may require ongoing noise monitoring, § 902.15.D.4 and D.6
As-built noise violation treated as a violation of the ordinance, § 902.15.D.6.c
Section 902.15.D.3 requires compliance with the noise standards to be determined by a Township-approved acoustical engineer at the applicant's expense, but it does not provide for applicant-paid consultant review of the studies in land development review.
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the I1 Industrial District