Kennett Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Kennett Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Kennett Township
The Planning Commission reviewed the first draft on August 11, 2026, and the township expects to present a second draft before the end of 2026.Kennett Township, Chester County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places and minimum site-size requirements. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements25
  • Only a 500-ft setback from non-intensive agriculture, § 240-1936.B

  • District height for data centers; 20 ft for ancillary uses, § 240-1936.D.9

  • Section 240-1936.A requires 1,000 ft from another existing data center, and the Data Center Campus definition is used only to waive that buffer for buildings in one unified development, so commonly controlled lots are not regulated as one use.

  • Section 240-1936.H requires Board approval for any increase in water demand, nameplate capacity, or utility service request, and Section 240-1936.I requires conditional use approval for expansion, but no like-for-like replacement exemption is stated.

  • 70 dBC day and 60 dBC night only, § 240-1936.F.10.a

  • 70 dBC day and 60 dBC night, § 240-1936.F.10.a

  • Pre-construction study and post-construction study within 180 days, § 240-1936.G.7

  • 65 VdB limit with vibration study, § 240-1936.F.10.b

  • Public water and water supply documentation required, § 240-1936.E.1 and F.1

  • Usage caps in a required community benefits agreement and a drought response plan, § 240-1936.E.6.b and G.3.

  • Wastewater plan including HVAC discharge with application, § 240-1936.G.3.

  • EPA Tier 4 diesel generators; no required emissions testing, § 240-1936.G.2

  • Thermal impact plan evaluating waste heat reuse, § 240-1936.G.4.

  • E-waste plan for servers, batteries, and hazardous materials, § 240-1936.G.5.

  • Energy plan; 10% renewable purchase over 50 MW, § 240-1936.G.2

  • Substations at side or rear and screened; lines 34.5 kV and below buried, § 240-1936.F.6

  • 50-ft landscape buffer, § 240-1936.F.8

  • Equipment screened on all sides, § 240-1936.F.9.b

  • Plan accepted by fire department, radio coverage, 24-hour signage; no annual update, § 240-1936.G.6

  • Fuel tank setbacks from homes and wells; no spill containment, § 240-1936.F.5

  • Annual fire safety inspections, § 240-1936.G.6.a

  • Closure notice and removal within 18 months; security optional, § 240-1936.J

  • One post-construction study, § 240-1936.G.7.d

  • Section 240-1936.E.6.b makes breach of the community benefits agreement a violation and grounds for revocation of occupancy permits, but no notice and hearing precede revocation and Sections 616.1 and 617.2 of the Municipalities Planning Code are not cited.

  • Applicant public meeting before Planning Commission review, § 240-1936.E.5

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use, large sites in LI only