Borough of Jim Thorpe

Anti-Data Center Policies

Jim Thorpe Borough’s enacted ordinance allows data centers but requires cooling and water-use controls, noise limits and testing, and setbacks from homes and other protected places, increasing project costs.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Jim Thorpe Borough
Borough Council adopted Ordinance No. 2026-03 on August 13, 2026, and it is codified as Section 500-103 of the Zoning chapter.Jim Thorpe Borough, Carbon County — data-center ordinance (No. 2026-03)

What this means

The measure imposes cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements18
  • 67 dBA day and 57 dBA night at the property line, § 500-103F(1)

  • Section 500-103F(1) requires sound studies with the application, at building permit, and six months after occupancy, using ANSI S1.4 meters and generally accepted methodology.

  • Generators barred from 8 p.m. to 8 a.m. except emergencies; no hours cap, § 500-103H(5)

  • Private wells barred for cooling makeup water; feasibility study for nonpublic sources without pump tests, § 500-103G and Q(3)

  • Closed-loop cooling required and evaporative cooling towers prohibited without an exemption, § 500-103Q(1).

  • Projected water demand disclosed; no cap, reporting, or drought plan, § 500-103G(5)

  • Section 500-103G(6) requires the applicant to demonstrate that domestic, cooling, and industrial wastewater disposal has been provided and approved by the Sewage Enforcement Officer or DEP.

  • Batteries, fuel, and refrigerants disposed of at decommissioning, § 500-103L(3)

  • Utility certification of capacity; no electrical inspection, § 500-103H(1).

  • Generation for normal operations is a separate use with its own approval, § 500-103H(2).

  • 25-ft planted buffer, § 500-103D(1)

  • Equipment within 300 ft enclosed or screened and rooftop equipment screened; no 12-ft standard, § 500-103E and J(2)

  • Plan accepted by the fire department with 24-hour contacts; no annual updates or radio coverage, § 500-103I(1)

  • Applicant must ensure first responder training, § 500-103I(1)(d)

  • Annual fire safety inspections, § 500-103I(1)(e)

  • Construction hours of 7 a.m. to 6 p.m.; no haul routes or road bond, § 500-103O

  • Plan with start within 1 year and completion within 18 months; no financial security, § 500-103L

  • One as-built sound study after opening, § 500-103F(1)(c)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Special exception in the Industrial District