Jackson Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Jackson Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Jackson Township
The Board of Supervisors scheduled a public hearing on the amendment for July 27, 2026, and no record of a vote or adoption had been posted or reported as of October 6, 2026.Jackson Township, Columbia County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and limited eligible locations. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements26
  • Section 4.1 establishes the Data Center Overlay District as shown on the Official Zoning Map, and Section 4.4 states that no Data Center shall be permitted outside it.

  • Conditional use; no approval expiration, Section 7

  • 50-ft building and 65-ft equipment limit, Section 8

  • Environmental impact statement required, Section 10

  • Section 6.A.3 defines a Data Center Campus as buildings on a unified tract or assemblage of parcels under common ownership or control, Section 7.A permits the campus as one conditional use under one Master Plan (Section 9), and Section 8.G requires one mile between data centers on separate properties.

  • Section 7.E bars a later phase until prior phases comply, and Section 9.E requires the Energy Demand Analysis to state projected electrical demand for each phase of development.

  • 55 dBA day and 50 dBA night at the property line, Section 9.C

  • Section 9.C requires preliminary, interim, and as-built noise studies, with measurements under ANSI S1.4-2014, but does not require the as-built study to be taken at full operating load.

  • Section 9.J sets 0.1 in/sec PPV at the property line and requires a Vibration Impact Study using PPV or the then current industry standard, but names no measurement standard or procedure.

  • Monthly water use reporting; no drought plan, Section 14

  • Cooling may produce no wastewater or discharge, Section 11

  • DEP and EPA air standards; Tier IV only if required, Sections 9 and 11.G

  • Heat plume mitigation plan; no reuse review, Sections 6 and 10

  • Utility capacity letter with application; no electrical inspection, Sections 9.E and 10.

  • Substations screened and part of the use, Sections 6 and 9.K

  • Utility must state required upgrades and responsibility, Section 9.E

  • Buffering required; no width, Section 9.K

  • Equipment screened from roads and neighbors, Section 9.K

  • Emergency plan with 24-hour contacts; no annual update or radio, Section 9.F

  • BESS spill containment; no storage setbacks, Section 9.N

  • Section 10.H lists a Traffic Impact Study among the required application contents but states no scope, so construction traffic and the study area are not addressed.

  • Work hours and truck routes; no road bond, Section 13

  • Financial security after 12 months inactive; no 110% or 6-month removal, Sections 9.M and 15

  • Continuous noise, monthly water, annual energy reports, Section 14

  • Section 17 makes violations zoning violations enforced under the Zoning Ordinance and the MPC and states that approvals may be revoked, but gives no revocation grounds, notice, or hearing.

  • Applicant pays for decommissioning and violation reviews only, Sections 9.J and 9.M

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in a Data Center Overlay District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data