Loading map…

Howe Township

Anti-Data Center Policies

Howe Township allows data centers but requires cooling and water-use controls, noise limits and testing, and setbacks from homes and other protected places, adding construction and compliance costs.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Howe Township
The rules are in the restated Zoning Ordinance, Ordinance No. 26-02, which the Board of Supervisors adopted with the Zoning Map on July 2, 2026, according to the meeting minutes the township secretary provided and the ordinance cover page.Howe Township, Perry County — data-center ordinance (No. 26-02)

What this means

The measure imposes cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements21
  • Conditional use with Board of Supervisors hearing, § 1001F; no approval expiration

  • Underlying 60-ft height limit, §§ 1002.I.5, 903

  • Single limit of 55 dBA or ambient at the property line, § 1002.I.8

  • Applicant ambient noise study before approval only, § 1002.I.8

  • Generators covered by noise limit only, § 1002.I.8.a

  • Must use public water; private supply study by hydrogeologist, no pump tests, § 1002.I.11

  • Air-cooled or closed-loop cooling required; other systems case by case, § 1002.I.11.b.

  • Projected water demand disclosed, § 1002.I.11.d

  • Public sewer will-serve letter and DEP approval for discharges, § 1002.I.11

  • E-waste plan for servers, batteries, hazardous materials; refrigerants not named, § 1002.I.13.b

  • Interconnection agreement required; no electrical inspection, § 1002.I.10.a.

  • Private energy facilities covered by noise limit, § 1002.I.8

  • All electric lines underground; equipment screened; substation placement not set, § 1002.I.6, I.10.d

  • Rate impacts assessed; developer must mitigate rate increases, § 1002.I.10.c

  • 100-ft planted buffer with berm next to residential uses, § 1002.I.7.

  • Equipment screens compatible with building facade, § 1002.I.6.a

  • Equipment screened on all sides with acoustic barriers near homes; no 12-ft height, § 1002.I.6, I.8.b

  • Plan reviewed by fire chief with 24-hour contact; no annual update or radio coverage, § 1002.I.12

  • Plan must ensure first responder training; no funding, § 1002.I.12

  • Annual fire safety inspections, § 1002.I.12

  • 125% security net of salvage; no closure notice or removal deadline, § 1002.I.13

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the C Commercial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data