Hopewell Township
Anti-Data Center Policies
Hopewell Township’s enacted ordinance requires data centers to be set back from homes and other protected places. Approval remains possible, but the limits significantly narrow where projects can be sited.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Hopewell TownshipThe current rules are in Ordinance 5-2026, which the Board of Supervisors adopted on May 7, 2026.Hopewell Township, York County — data-center ordinance (No. 5-2026)
What this means
The measure imposes setbacks from homes or other protected places. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements27
300 to 500-ft buffer yards along lines within 500 ft of schools, day care centers, hospitals, and parks, § 27-504.7CC(1)(b)
Underlying zone height; rooftop equipment set back and screened, § 27-504.7CC(1)(a)(7) and (f)(7)
Environmental impact assessment required, § 27-504.7CC(1)(l)
Single 24-hour CNEL limit of 60 dBA at sensitive receptors and 70 dBA elsewhere, § 27-504.7CC(1)(c)(1)
Section 27-504(7CC)(1)(c)(6) requires preliminary, interim, and as-built sound studies by an INCE Board Certified engineer, reviewed by a Township-selected noise engineer, with the as-built study before occupancy, but names no measurement method or standard and requires no measured study at full operating load after opening.
0.2 in/s peak particle velocity limit with pre- and post-construction studies; not a no-perceptible standard, § 27-504.7CC(1)(i)(4)
Public water required and water feasibility study; no pump tests, § 27-504.7CC(1)(e) and (j)
Best available cooling technology must be shown; closed loop not required, § 27-504.7CC(1)(q)
Projected water needs disclosed, § 27-504.7CC(1)(j)
Public sewer required and water release identified, § 27-504.7CC(1)(e) and (j)
Stormwater management plan required, § 27-504.7CC(1)(l)
Air permit applications and final permits provided to the Township; no Tier 4 rule, § 27-504.7CC(1)(l)
Waste heat potential considered in cooling selection, § 27-504.7CC(1)(q)
Hazardous materials removed and disposed of at decommissioning, § 27-504.7CC(1)(r)(4)
Utility capacity letter and third-party electrical inspection before occupancy; no confirmation before approval, § 27-504.7CC(1)(e)(1)
Rooftop solar required on buildings over 250,000 sq ft where feasible; no energy usage plan, § 27-504.7CC(1)(p)
Substations 300 ft from homes and lines of 34.5 kV or less buried; substations not screened, § 27-504.7CC(1)(d) and (e)
Planted buffer yard of 300 to 500 ft next to residential property, § 27-504.7CC(1)(b).
Rooftop equipment screened on four sides and ground equipment screened for sound; no 12-ft standard, § 27-504.7CC(1)(c) and (f)
Architectural depictions from all lot lines and streets; no viewshed study, § 27-504.7CC(1)(f)(6)
In-building radio coverage and fire chief review; no emergency plan, § 27-504.7CC(1)(h) and (k)
Third-party electrical inspection before occupancy; no annual inspections, § 27-504.7CC(1)(e)(1)
110% security with no salvage credit, but no removal deadline or closure notice, § 27-504.7CC(1)(r)
Estimate and security updated every 5 years, not after the first year, § 27-504.7CC(1)(r)
As-built sound study and one post-construction vibration study, § 27-504.7CC(1)(c)(6) and (i)(4)
Sound study reviewed by a Township-selected engineer; cost not assigned, § 27-504.7CC(1)(c)(6)
Responsible party named in the decommissioning plan; end user not required, § 27-504.7CC(1)(r)(2)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Special exception in the Commercial and Industrial zones
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data