Hopewell Township

Anti-Data Center Policies

Hopewell Township’s enacted ordinance limits data-center locations through setbacks from homes and other protected places, minimum site sizes, and restricted eligible areas, substantially narrowing workable sites and designs despite an approval route.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Hopewell Township
The rules are in Section 320-1015 of the township code, added by Ordinance No. 01-2026 on July 13, 2026 according to the codified text on eCode360, and on-site power generation is regulated separately as its own use under the Fossil Fuel Electric Generating Facilities Ordinance of 2026 (Ordinance No. 02-2026).Hopewell Township, Washington County — data-center ordinance (No. 01-2026)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and limited eligible locations. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.

Restrictions & requirementsHide restrictions & requirements33
  • Conditional use in the IND-1 Limited Industrial District only, and not a permitted use or special exception in any other district, § 320-1015B(1)

  • Conditional use decided by the Supervisors; approval expires if a zoning permit, building permit, or occupancy certificate is not obtained within 12 months, or 24 months with land development, § 320-601J

  • 80 ft maximum including all rooftop equipment; no showing that this is within the IND-1 limit for other buildings, § 320-1015B(4)(e)

  • Environmental Impact Assessment required before construction; no riparian buffer, § 320-1015B(36)

  • Chapter 187 limits of 55 dBA daytime and 45 dBA nighttime at the property line or nearest residential receptor apply, with ANSI and ISO measurement; daytime limit above 50 dBA, § 320-1015B(25) and § 187-6A, B, and E(4)

  • Octave band limits of 65 dB at 31.5 Hz and 60 dB at 63 Hz with a tonal penalty; no 125 Hz or dBC limit, § 187-6E

  • Pre-construction study and a post-construction study before the occupancy permit, by a certified noise engineer; no measured study at full operating load after opening, § 320-1015A(1)(c) and B(24)

  • Non-emergency generator operation limited to 8:00 a.m. to 8:00 p.m. weekdays, with maintenance runs capped at 120 hours per generator per year, § 320-1015B(9) and B(39)

  • Ground-borne and structural vibration may not exceed the ISO residential day curve of 200 um/s in any one-third octave band, with noise and vibration studies, § 320-1015B(24) and B(37)

  • Analysis of anticipated public water needs and a water provider capacity letter with the executed agreement; public water not mandated and no well study, § 320-1015B(10)

  • Latest water conservation technology required, including closed loop systems; no evaporative system limit, § 320-1015B(34)

  • Anticipated water needs disclosed; no metered reporting or drought plan, § 320-1015B(10)

  • Disposal of domestic, cooling, and industrial wastewater must be provided for and approved by DEP, with chemicals listed, and no ground may be broken before all permits issue, § 320-1015B(11) and B(40)

  • Tier 4 generators or EPA Tier 4 Final required; annual reports cover efficiency and generator hours, not emissions, § 320-1015B(33) and B(39)(d)

  • E-waste disposed of at an approved site and recycled through certified facilities at decommissioning; no plan or disposal contract, § 320-1015B(48)(b) and B(49)

  • Energy efficient technology and annual efficiency report only; no energy plan, § 320-1015B(33)

  • Power lines from the data center placed underground, except switchyards and substations; substation placement and screening not addressed, § 320-1015B(30)

  • Battery storage must meet NFPA 855 with battery-specific fire suppression, § 320-1015B(8)

  • Utility letter must state the potential impact on the grid and the executed agreement must be filed; no upgrade cost or tariff terms, § 320-1015B(6)

  • 100-ft buffer of native evergreen and canopy plantings next to residential, commercial, and agricultural districts; no replacement of dead plants, § 320-1015B(28)

  • Fenestration with horizontal and vertical breaks every 35 lineal feet, low-reflective earth tone colors, and roofline variation, § 320-1015B(15) and B(23)

  • All rooftop and ground equipment fully screened from view with screening placed to shield noise, and equipment near roads, districts, and sensitive receptors fully enclosed, § 320-1015B(24)(a) and (b) and B(26)

  • Licensed architect renderings with elevations required; no visual impact study from roads or historic sites, § 320-1015A(1)(a)

  • Hazardous Materials Plan required; no storage setbacks or containment standard, § 320-1015B(50)

  • ERP provides for annual fire safety inspections by a qualified professional; no report to a municipal fire official, § 320-1015B(43)(e)

  • Township Traffic Impact Study requirements apply; scope not stated, § 320-1015B(35)

  • Construction truck routes, a road maintenance agreement, and a road bond; no construction hours, § 320-1015B(17) to (19)

  • 125 percent security, plan recorded with the Recorder of Deeds, and removal within 60 plus 180 days of a final determination made after 12 months of inactivity, beyond 6 months, § 320-1015B(47)

  • Cost estimate and security updated every three years and at transfer; no update after the first year, § 320-1015B(47)(b)[5] and (e)[4]

  • Continuous sound monitoring accessible to the township under Chapter 187, annual generator hour reports, and annual efficiency reports, § 320-1015B(25), B(33), B(39)(d), and § 187-6F

  • Chapter 187 allows suspension or revocation of approvals for continued noise violations, but no notice and hearing are stated; general penalties otherwise, § 320-1015D and F and § 187-11E

  • All studies and monitoring at the operator expense and the township may inspect independently; consultant review fees not assigned, § 320-1015A(1)(e) and B(32)

  • Affidavit or agreement between the landowner and the data center owner or operator required; no end user, § 320-1015B(5)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the IND-1 Limited Industrial District