Honey Brook Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Honey Brook Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Honey Brook Township
The Board of Supervisors scheduled a public hearing on the draft for October 14, 2026, and on October 21, 2026 the township said it will email a copy of the ordinance once all of the Supervisors have signed it.Honey Brook Township, Chester County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose cooling and water-use rules, setbacks from homes or other protected places and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements31
  • Conditional use hearing before the Board; approval expires without construction in 12 months, § 27-1067.C.3 and C.8

  • Section 27-1067.D.4 sets an all-inclusive 35 foot limit covering the roofline, parapets, and all mechanical equipment, with rooftop equipment recessed 5 feet below the roofline, but the BI district height limit for other principal buildings is not in the ordinance text read.

  • 150-ft water resource setback plus base riparian rules; no steep slope widening, § 27-1067.D.2.d

  • 55 dBA day and 52 dBA night hard caps, § 27-1067.G.1.c

  • Section 27-1067.G.1.a caps sound at 1 dBA above the pre-construction ambient level from two 30-day baseline studies that use the quietest night hour, measured as Leq (G.1.b), but the baseline is not defined as L90 and no floor is set below which the cap does not apply.

  • 65 dBC single limit, § 27-1067.G.3

  • Two baseline studies and audits at 30 days and 6 months; none at building permit, § 27-1067.G.5

  • Section 27-1067.H.4.f limits routine generator testing to 10:00 AM to 4:00 PM, Monday through Friday, excluding federal holidays, at no more than 1 hour per generator per month and 60 hours per month in total, and Section 27-1067.H.4.e allows operation as otherwise required by law.

  • Public water will-serve required; private wells barred for cooling, § 27-1067.H.2-3

  • Closed-loop air-cooled required; evaporative cooling prohibited, § 27-1067.H.2

  • Use capped at provider allocation, real-time monitoring, drought stress test, § 27-1067.H.3 and H.5.

  • Section 27-1067.H.3.c(3) classifies blowdown as industrial waste, requires a Wastewater Characterization Study, and permits sewer discharge only with an approved pre-treatment agreement and a DEP WQM permit, or else a zero liquid discharge system or licensed hauler contract, but the approvals are not required before the zoning permit.

  • Section 27-1067.H.3.c(4) designates the site a Stormwater Hotspot with structural BMPs treating 100 percent of runoff for hydrocarbons and heavy metals, but no spill containment is required for fuel, generator, and transformer areas (the Section 27-1067.J secondary containment covers fire suppression water).

  • EPA Tier 4 Final generators with annual testing reports, § 27-1067.H.4.e

  • Heat island limit with CFD modeling; no waste heat reuse review, § 27-1067.G.8.b

  • Utility certification and interconnection agreement; no electrical inspection, § 27-1067.H.4.a.

  • Grid impact study; no renewable requirement, § 27-1067.H.4.b

  • On-site lines buried; substations excluded as accessory uses but not screened, § 27-1067.E.1 and § 27-202

  • Section 27-1067.H.4.a to c require an Interconnection Agreement, a Grid Impact Study identifying required transmission upgrades and off-site improvements, and a Service Impact Analysis certifying applicant funding, but no estimated upgrade cost or tariff terms are required.

  • Berm and double row of evergreens; buffer width not stated, § 27-1067.F.1-2

  • Visual impact evaluation from roads and lot lines; no renderings required, § 27-1067.M.2

  • Plan approved by fire chief and officials; no annual update stated, § 27-1067.J.1

  • Hazardous materials inventory and fire water containment; no storage setbacks, § 27-1067.M.2.c and J

  • Annual Building Code Official inspections funded by escrow, § 27-1067.S.2

  • Section 27-1067.M.2.a(3) requires a traffic study in every Environmental and Community Impact Analysis covering trip frequencies and types, heavy equipment delivery during construction, and fuel deliveries, but no study area reaching the nearest arterial or interchange is stated.

  • Road restoration after trenching; no hours, routes, or bond, § 27-1067.E.2

  • 150% security; removal within 12 months after a 6-month start, § 27-1067.P

  • Security reviewed every 3 years, § 27-1067.P.2

  • Section 27-202 defines High-Density Digital Processing to include cryptocurrency mining and AI model training and High-Intensity Data Centers regardless of building size, and treats a data center as an accessory use only below the lesser of 2,500 square feet or 15 percent of floor area and 1 MW of electrical infrastructure.

  • Annual certification, quarterly reports, and real-time monitoring, § 27-1067.G.5 and H.5

  • Section 27-1067.S.1 requires an Administrative Escrow at the time of the conditional use application to pay the Township's consultants to review the application, fact-check studies, and testify at hearings, which is review at the zoning stage rather than in land development review.

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the BI district

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data