Hazle Township

This restriction takes precedence for the map color while in effect.

Anti-Data Center Policies

Hazle Township has enacted a pause on covered data-center applications or development for 180 days, temporarily preventing affected projects from moving ahead, but not permanently banning them.

Rating from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Hazle Township.

Incentives

Financial Incentive
2

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Hazle Township
The supervisors unanimously declared the zoning ordinance invalid for failing to address data centers and began a 180-day pause while a curative amendment is prepared.Hazle Township, Luzerne County — data-center moratorium / curative resolution curative resolution (2026-06-08)

What this means

The measure pauses covered data-center applications or development for 180 day. That stops affected projects from moving ahead during the pause, even though it is not a permanent ban.

Timing

Ends
180-day; exact operative ending date not independently verified.

The supervisors unanimously declared the zoning ordinance invalid for failing to address data centers and began a 180-day pause while a curative amendment is prepared.

Sources

pending · Hazle Township
The text is Discussion Draft #2, dated October 26, 2026, of an amendment to Zoning Ordinance No. 2003-1-6-1 that follows the supervisors' June 8, 2026 declaration of invalidity and 180-day pause, an earlier October 20 draft described by the Times Leader would have required a special exception, and the Planning Commission scheduled a special public meeting on October 29, 2026 to take comment, with no supervisors' hearing or vote date posted.Hazle Township, Luzerne County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements32
  • Permitted only in the I-1 district within an area described by the 230 kV line, I-81 and SR-924, Sections 505.1 and 802.54.B(1) and (8); exclusion from other districts not expressly stated and no mapped overlay in the text

  • Section 505.1 adds data centers as permitted uses in the I-1 district, with no conditional use or special exception review.

  • 1,250 ft from residential district lots and sensitive receptors, reducible to 1,000 or 500 ft at 5 or 10 dBA below the limit, measured from buildings, generator yards and outdoor mechanical equipment areas, Section 802.54.B(2)(a)-(d)

  • Sensitive receptors include schools, hospitals, nursing homes, day care and places of worship but not parks, and the setback can fall to 500 ft, Sections 202 and 802.54.B(2)

  • 100 ft from streams and regulated waterbodies, waivable with studies and permits, not widened for slopes or wetlands; natural resource analysis and wetland evaluation required, Section 802.54.B(2)(g) and C(4)(b)-(d)

  • Commonly controlled lots treated as one unified development tract; no separation between data centers or combined limits, Section 802.54.B

  • Each phase of a Construction Phasing Plan reviewed by the Township Engineer with updated studies possible; no electrical demand by phase or stated triggers for new approval, Section 802.54.A(3)

  • Single 55 dBA day-night average (DNL) limit at the sensitive receptor lot line or residential district boundary, ANSI S1.4 meters, Section 802.54.J(5)(b)

  • Preliminary, interim and as-built studies with ongoing yearly monitoring, but the as-built study covers normal operations rather than full operating load and the predictive method is not stated, Section 802.54.J(5)(d)-(g)

  • Public or central water required; no hydrogeologic study or pump test for on-site sources, Section 802.54.E(1)

  • Closed-loop or non-water cooling, or evaporative cooling only with reclaimed or non-potable water; no water-use rate for evaporative systems, Section 802.54.E(2)

  • Annual cooling water use reported to the Township; no drought plan, Section 802.54.E(2)

  • Public or central sewer required and sewage planning module submitted with the application; agency approvals not required before the zoning permit, Section 802.54.E(1)-(2) and J(8)

  • Diesel generators must meet EPA Tier 4 standards; no annual emissions testing or reports, Section 802.54.J(15)(c)

  • Heat Mitigation Plan with waste heat reuse or dissipation strategies; no modeled property line temperature effects, Sections 802.54.C(6)(j) and 802.55.O(5)

  • Hazardous Materials and Electronic Waste Plan for lawful disposal; no storage plan for refrigerants or disposal contract, Sections 802.54.C(6)(i) and 802.55.O(4)

  • Interconnection documentation required before a building permit for the first data center building, Section 802.54.J(9)

  • Substations serving a data center are accessory uses with a 500 ft setback from residential lots and sensitive receptors; no placement or burial rule, Sections 505.1 and 802.54.B(2)(e)

  • Energy storage must meet NFPA 855 and UL 9540A with suppression and gas detection; no battery setbacks, hazard mitigation analysis or battery emergency plan, Section 802.54.J(14)(f)-(g)

  • Buffer of at least 50 ft plus a 30 ft mounded planted buffer, year-round screening and replacement of dead plants; minimum width under 100 ft, Section 802.54.F(2)-(6)

  • Rooftop equipment screened by parapet, generator groups fenced or walled, and equipment attenuated as needed to meet noise limits; not all ground equipment screened to its height, Section 802.54.F(12), J(5)(c) and J(15)(b)

  • Viewshed analysis and elevations required; no roads, historic sites or renderings specified, Sections 802.54.C(4)(f), C(6)(d) and 802.55.O(2)

  • Emergency plans reviewed by the Fire Chief with annual facility tour; no annual update or posted 24-hour contacts, Section 802.54.C(4)(i)5 and J(11), J(14)(b)

  • Owners must participate in annual training with the fire company; no applicant-delivered training before occupancy or equipment at no cost, Section 802.54.J(14)(b)

  • Hazardous materials plan and containment information required; no storage setbacks from wells or streams, Section 802.54.C(6)(g)3 and (i)

  • Annual Fire Prevention Inspection referenced for fire water supply; no report or correction deadline, Section 802.54.J(14)(c)

  • Traffic impact study with every preliminary application and a construction transportation plan; study area not stated, Section 802.54.J(4) and C(6)(h)

  • Construction days and hours limited and construction transportation plan required; no road posting or excess maintenance agreement, Section 802.54.C(3) and C(6)(h)

  • Security of 110 percent, but 18 months for removal and reusable buildings may remain with no time limit, Section 802.54.J(16)

  • Estimate updated every five years with security adjusted; no update after the first year, Section 802.54.J(16)(b)2.b

  • Yearly sound monitoring with automatic noncompliance notice and annual cooling water use reports, Section 802.54.E(2) and J(5)(g)-(j)

  • Township Engineer reviews phases and cost estimates; fees for consultant review not assigned to the applicant, Section 802.54.A(3) and J(16)(b)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: permitted use in the I-1 district within a designated area (working draft)