Hanover Township
Anti-Data Center Policies
Hanover Township’s enacted ordinance requires data centers to meet minimum site sizes and keep setbacks from homes and other protected places. Projects can still be approved, but these requirements add costs.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Hanover TownshipThe current rules are in Ordinance No. 148, the Hanover Township Data Center Ordinance of 2026, which the Board of Supervisors enacted in March 2026 with a signature page dated March 20, 2026.Hanover Township, Washington County — data-center ordinance (No. 148)
What this means
The measure imposes setbacks from homes or other protected places and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements20
Base district height limit applies; rooftop screening only, Section 4.A
Natural resource inventory (PNDI) and geotechnical report; no riparian buffer, Section 4.C(3) and (9)
Data Center Park of three or more data centers defined as one planned development, Section 3
Base ordinance noise limits of Section 1201.2 apply, Section 4.B(1)
Section 4.B(1)(b) requires a preliminary sound study at conditional use, a study at pre-construction plan review, and a post-construction study six months after the certificate of occupancy along all property lines, but names no measurement method and does not require full operating load.
Public water required and water impact study on nearby wells; no pump tests, Section 4.B(5)(c)
Section 4.B(5)(c)(ii) and (v) require annual water usage reports to confirm compliance with permitted use and conservation during drought conditions, but the drought measures are not tied to state, basin commission, or supplier drought declarations and metering is not stated.
Section 4.B(5)(c)(iv) and (vii) require a capacity letter from the public sewage utility and a showing that disposal of domestic, cooling, and industrial wastewater has been provided and approved by the Sewage Enforcement Officer or DEP, but do not state that the approval must be in hand before the zoning permit.
Utility capacity certification; no third-party electrical inspection, Section 4.B(4)(a)(iii).
Independent power generation is a separate use with its own approval, Section 4.B(4)(a)(ii).
Substations included in accessory equipment that must be screened, Section 3 and Section 4.A.2.b
Rate impacts and required infrastructure improvements disclosed, Section 4.B(4)(a)(iii) and C(5)
50-ft planted buffer yard next to residential and agricultural districts, Section 4.A.3
Equipment screened to 12 ft on the ground and 10 ft on roofs, with noise equipment in sound-attenuating enclosures, Section 4.A.2.b and B(1)(c).
Emergency plan approved by the fire department, annual drills, and 24-hour contact; no in-building radio coverage, Section 4.B(6) and 4.G
Hazardous materials plan and spill containment; no storage setbacks, Section 4.B(6)(a)(xi) and C(4)(b)
School traffic coordination only
150% bond less salvage value; no removal deadline or closure notice, Section 4.B(5)(b)
Security amount reviewed annually, Section 4.B(5)(b)(ii)
Annual water usage reports and noise monitoring reports on request, Section 4.B(1) and B(5)(c)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the I-B Industrial and Business and S-D Special Development Districts