Hanover Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Hanover Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Hanover Township
The unnumbered 2026 draft, which amends the Zoning Ordinance of June 2, 2025, was listed for Planning Commission review on October 6, 2026 and posted in a township information packet on October 8, 2026, and the commissioners have scheduled a public hearing for December 9, 2026 at 5:30 PM.Hanover Township, Luzerne County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and limited eligible locations. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.

Restrictions & requirementsHide restrictions & requirements37
  • Data centers and campuses permitted only on property in the DC-O overlay mapped as Exhibit A, and listed as not permitted (N) in the I-2 District in Exhibit B, Section 3 B.1 and Section 2

  • Conditional use under Article 7 with Section 704 general standards, Section 4 and Section 3 B.1; no lapse period for the approval found

  • 500 ft setback from the exterior boundary of the Unified Tract for principal buildings and for accessory structures and equipment, Section 801.52 E.3

  • 65 ft limit including rooftop appurtenances and roof-mounted equipment, Section 801.52 E.4; the I-2 base height limit was not compared

  • Contiguous lots under common control developed as one Unified Tract under one conditional use approval, with standards measured from the tract boundary, Section 1 F and Section 801.52 D; no separation between campuses

  • 55 dBA daytime and 45 dBA nighttime and weekend at the Unified Tract boundary, measured as 10-minute LAeq with ANSI S1.4 meters, Section 801.52 L.B(1)(d) and (e); the daytime limit is above 50 dBA

  • Where baseline exceeds the limit, operations may not materially increase measured baseline ambient noise, Section 801.52 L.B(1)(c); no numeric cap or floor

  • Infrasound below 20 Hz limited to 80 dB(Z) and full-spectrum modeling with octave band analysis required, Section 801.52 L.B(1)(a), (b) and (d); no dBC or octave-band limits

  • Predictive worst-case study with the application, update before building permits, and as-built test within 90 days of occupancy by a stated method, Section 801.52 L.B(1)(g); the as-built test is at representative normal operations, not full load

  • Non-emergency generator testing only 9:00 AM to 5:00 PM on weekdays, excluding federal holidays, with two weeks notice, Section 801.52 L.B(1)(i); no hours cap

  • Vibration study by a licensed PE and no vibration perceptible beyond the tract boundary, Section 801.52 M; no numeric limit

  • Private wells and surface water withdrawals barred for cooling, public water capacity confirmation required, and any groundwater withdrawal requires a feasibility study with drawdown and recovery testing of pumped and observation wells, Section 801.52 O.1, O.2, O.3 and O.5

  • Closed-loop non-evaporative cooling required and open-loop systems prohibited, Section 801.52 O.3 and O.7

  • Annual report of total water consumed, Section 801.52 O.10; drought plan only if the Township declares a shortage, O.8

  • Domestic and cooling-related wastewater disposal through facilities approved by the Sewage Enforcement Officer or DEP must be demonstrated, and cooling water disposal requires DEP approval, Section 801.52 O.3 and O.9

  • Impervious coverage allowance conditioned on the Township stormwater ordinance and state permits, Section 801.52 E.6; no added treatment for fuel or equipment areas

  • Tier 4 diesel, natural gas, or propane generators for emergency use only, cleaner models required when available, and state and federal air rules apply, Section 801.52 C.A and C.B; no annual emissions testing or reports

  • Batteries, fuel, and refrigerants disposed of under state and federal law at decommissioning, Section 801.52 T.4

  • Utility documentation that 230 kV service is feasible, such as a will-serve letter or interconnection correspondence, submitted with the conditional use application, Section 801.52 A.2 and P.1; no firm capacity confirmation or service agreement before the zoning permit

  • Generation supplying power during normal operations is a separate principal use subject to all zoning, permitting, and approval requirements for that use, Section 1 A, Section 801.52 C.D and P.2; P.5 separately calls behind-the-meter generation permissible

  • Data center substations must have year-round opaque landscaping or an 8 ft screen wall, Section 801.52 P.3; no placement or line burial standard

  • Battery storage must meet NFPA 855 and fire codes with suppression and monitoring, Section 801.52 Q.2

  • Known or anticipated impacts on electric rates or availability attributable to the project must be noted, Section 801.52 P.1; no cost assignment or service agreement

  • 100 ft planted buffer along boundaries abutting residential districts or uses, mostly native with evergreen trees every 25 ft, maintained for the life of the use and dead plants replaced within 90 days, Section 801.52 H

  • Full-cutoff downward fixtures, shielded equipment, and no light source visible from adjacent residential properties, Section 801.52 N; no light trespass limit at the property line

  • Equipment within 500 ft of residential districts or roads fully enclosed or fully screened, and rooftop equipment screened to the maximum extent practicable, Section 801.52 I and K.3

  • Architectural elevations of all sides required, Section 801.52 K.5; no visual impact study or renderings

  • Emergency response plan by a qualified professional submitted to the fire department and emergency management agency for comment, Section 801.52 Q.1 and Q.3; no annual update or walk-through

  • Funded first responder training before operations and at least annually, Section 801.52 Q.1.D; no on-site specialized equipment requirement

  • Fuel tanks and other equipment set back 500 ft from the tract boundary, and hazardous substance uses are conditional, Section 801.52 E.3 and Exhibit B; no containment or spill plan

  • Annual fire and life-safety inspections by a qualified professional, with reports provided to the Township on request, Section 801.52 Q.1.E; no correction deadline

  • Primary access to an arterial or collector street required, Section 801.52 A.4; no secondary emergency access required

  • Decommissioning plan and financial security of at least 100% of cost, with removal starting within one year of cessation and finished within 18 months, Section 801.52 T; security below 110% and no recorded agreement

  • Annual reports on water and electricity use and an annual compliance certification by January 31, Section 801.52 O.10, P.7 and S

  • As-built noise noncompliance and non-emergency generator use are violations, Section 801.52 L.B(1)(g) and (i); no revocation grounds or MPC 616.1 and 617.2 reference

  • Township Engineer review of the decommissioning plan at applicant expense and operator reimbursement for confirmed noise exceedance testing, Section 801.52 T.1 and L.B(1)(h); other studies not covered

  • Ownership and site control documents required, Section 1 G; no requirement to name the operator or end user

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: Conditional use in the Data Center Overlay (DC-O) District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data