Hampden Township

Anti-Data Center Policies

Hampden Township requires data centers to meet setbacks from homes and other protected places and minimum site sizes. Approval remains possible, but these rules increase construction and review requirements.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Hampden Township
The current rules are in Ordinance No. 2026-03, which the Board of Commissioners adopted by a 5-0 roll call vote on July 2, 2026, after a public hearing, according to the approved minutes of that meeting.Hampden Township, Cumberland County — data-center ordinance (No. 2026-03 (Adopted July 2, 2026))

What this means

The measure imposes setbacks from homes or other protected places and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements24
  • Conditional use; no approval expiration, § 1504

  • Larger buffer yards near sensitive receptors, but no setback, § 1918

  • 35 ft, up to 50 ft with added setback; rooftop equipment screened, § 1918

  • 100-ft riparian buffer, wider on slopes and at wetlands, § 1918

  • Section 1918.I sets 50 dBA day and 40 dBA night and weekend limits at any point along the property line of an adjacent sensitive receptor, and Section 1918.I.5.A(4) requires all sound studies to use ANSI S1.4-2014 Type I meters with generally accepted methodology.

  • 55 dBC at residential property lines at all times, § 1918.I

  • Section 1918.I.5.A requires preliminary, interim (building permit), and as-built studies within three months of occupancy using ANSI S1.4-2014 Type I meters, but the preliminary study is due before building permit application rather than with the conditional use application, and the as-built study is not required at full operating load.

  • General vibration limit referenced; no study, § 1918.I

  • Water feasibility and hydrogeologic studies; no cooling-well bar, § 1918

  • Section 1918 requires quarterly reports of total daily water withdrawn to PA DEP and Hampden Township Public Works, and requires withdrawals for cooling to be suspended during DEP drought warning or emergency declarations and SRBC drought restrictions.

  • Wastewater disposal approval and quarterly monitoring, § 1918

  • Stormwater calculations and drainage plan required, § 1918

  • Testing may not exceed emissions limits; natural gas only; no Tier 4, § 1918

  • Utility capacity letter before approval and third-party electrical inspection, § 1918

  • Grid power required; no energy usage plan

  • Substations screened at side or rear; lines of 34.5 kV or less buried, § 1918

  • 200- to 300-ft buffers near sensitive receptors, § 1918.

  • Equipment fully screened with acoustic screening; no 12-ft height, § 1918.

  • Plan accepted by fire department with radio coverage; no annual update or 24-hour contacts, § 1918

  • Responder training required; no funding, § 1918

  • Section 1918 requires the emergency response plan to provide for annual fire safety inspections by a qualified professional on behalf of the data center and a third-party electrical inspection before occupancy, but no report to the municipal fire official and no correction deadline are required.

  • Full-cost security and 6-month notice; not 110%, § 1918

  • Security updated biannually, § 1918

  • Quarterly water, wastewater, and well reports, § 1918

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Industrial General (IG) district

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data