Greenfield Township
Anti-Data Center Policies
Greenfield Township’s enacted rules require data centers to keep setbacks from homes and other protected places and meet noise limits, including sound testing. Projects can still seek approval, but these limits narrow where and how they can operate.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Greenfield TownshipThe Board of Supervisors adopted the amendment by voice vote on April 7, 2026, with no ordinance number shown on the signed copy, and the Supervisors are scheduled to consider the proposed NorLACK zoning ordinance, under which data centers would not be permitted in the township, on November 10, 2026.Greenfield Township, Lackawanna County — data-center ordinance (Number Not Shown)
What this means
The measure imposes setbacks from homes or other protected places and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements23
Conditional use before the Planning Commission and Board of Supervisors; no lapse provision, Article IV
40 ft maximum inclusive of roof-mounted equipment; no tie to the district limit, Section 842.01(A)(1)
Water feasibility study addresses nearby surface waters only for nonpublic supply; no buffer or impact assessment, Section 842.01(A)(5)
65 dBA weekday daytime and 55 dBA night and weekend at the property line, ANSI S1.4 meters, Section 842.01(A)(3)
Preliminary study in the conditional use process, interim study at building permit, and as-built study six months after occupancy, using ANSI S1.4 meters, Section 842.01(A)(3)(i)-(iii)
Generator testing only 9:00 a.m. to 5:00 p.m. on weekdays, excluding federal holidays, with the schedule submitted for approval; no hours cap, Section 842.01(A)(3)
Vibration study showing no vibration perceptible beyond the property line; no numeric limit, Section 842.01(A)(4)
Public authority supply certification or water feasibility study for nonpublic sources; no pump test, Section 842.01(A)(5)
Water use by purpose, including cooling, disclosed in the feasibility study for nonpublic supply; no cooling method required, Section 842.01(A)(5)(iii)
Projected water demand disclosed and Susquehanna River Basin Commission approval above 100,000 gpd withdrawal or 20,000 gpd consumptive use; no reporting or drought plan, Section 842.01(A)(5)
Disposal of domestic and cooling wastewater must be provided and approved by the Sewage Enforcement Officer or DEP, Section 842.01(A)(6)
Generator emissions must comply with federal, state, and local air quality rules, with permits provided to the township, Section 842.01(A)(11)
Electric provider must certify that capacity is available and that it will serve the data center, Section 842.01(A)(7)
Electrical substations are part of the accessory use and subject to its 250 ft setback; no screening or burial standard, Sections 303 and 842.01(A)
Known impacts on electric rates or availability must be noted, Section 842.01(A)(7)
Use completely enclosed by a Buffer Area as defined in the base ordinance, with dead trees replaced; width not stated in the amendment, Section 842.01(A)(2)
Emergency Response Plan reviewed and accepted by the fire department and emergency management; no annual update, Section 842.01(A)(8)(i)
Plan must ensure first responders receive training on the installed system, Section 842.01(A)(8)(iv)
Generator fuel storage must meet hazardous materials rules with DEP and NFPA permits provided; no setbacks or spill plan, Section 842.01(A)(11)
Plan includes annual fire safety inspections by a qualified professional; no report to the municipality, Section 842.01(A)(8)(v)
Definition includes cryptocurrency mining, blockchain processing, and server farms; incidental computer exemption has no size or power limit, Section 303
One as-built sound study six months after occupancy, Section 842.01(A)(3)(iii)
As-built noise exceedance is a violation of the Zoning Ordinance; no revocation grounds, Section 842.01(A)(3)(iii)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the Industrial District