Greene Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Greene Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Greene Township
The township now posts draft Ordinance 2026-03 on its website, and the Board of Supervisors is scheduled to vote on it on November 10, 2026, with the draft's certificate citing an Erie Times-News advertisement on November 1, 2026.Greene Township, Erie County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements26
  • Conditional use hearing required; no one-year expiration of approval, § 1103.A

  • Noise Mitigation Plan only; no numeric limit, § 1103.C

  • Baseline study required but no cap above background, § 1103.C(1)(a)

  • Preliminary study in the conditional use process and post-construction study within 12 months of occupancy, § 1103.C(1)

  • Vibration study showing none perceptible beyond the property line, § 1103.C(2).

  • Independent water source with a certified Water Utilization Report; no pump tests, § 1103.E(1)-(4)

  • Closed-loop cooling required and open evaporative towers prohibited absent an exemption, § 1103.I.

  • Daily and peak intake volumes disclosed; no cap, reporting, or drought plan, § 1103.E(3)

  • Section 1103.F(1) requires the applicant to demonstrate that disposal of domestic, cooling, and industrial wastewater has been provided and approved by the Greene Township Sewer Authority or the Pennsylvania DEP, as a standard of the conditional use.

  • Backup generators must meet EPA Tier 4, with annual testing reports to the Township, § 1103.D

  • Thermal Impact Mitigation Plan including waste heat reuse, § 1103.J.

  • Electronic Waste Plan for servers, batteries, and hazardous materials, § 1103.G.

  • Power system capacity documented before conditional use approval; no electrical inspection, § 1103.E(6).

  • Energy Management Plan and good faith renewable efforts; no required on-site renewables, § 1103.E(1)-(2)

  • On-site generation addressed and must meet all regulations; not a separate use with its own approval, § 1103.E(4)

  • Accessory electrical substations screened; placement and line burial not addressed, § 1103.S(1)

  • 100-ft buffer along residential property and districts, § 1103.R(2).

  • Ground equipment enclosed or behind noise-absorbing barriers and rooftop equipment screened on four sides; no 12-ft standard, § 1103.S

  • Plan accepted by the fire department, with annual inspections and 24-hour contact signs; no annual update or radio coverage, § 1103.V

  • First responders must receive system-specific training; funding not assigned, § 1103.V(2)(d)

  • Spill prevention and secondary containment for hazardous fluids; no storage setbacks, § 1103.K

  • Annual fire safety inspections, § 1103.V(2)(e)

  • Vehicle trips described in the impact analysis; no traffic study, § 1103.A(1)

  • 110% security; removal begins within 1 year and ends within 18 months; no closure notice, § 1103.W

  • Annual generator testing reports and a post-construction noise study; no ongoing noise, water, or power reports, § 1103.C, D

  • Owner pays the Township's review costs for decommissioning estimates only, § 1103.W(8)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data