Borough of Gratz

Anti-Data Center Policies

Gratz Borough’s enacted ordinance limits noise, requires sound testing, and sets buffers from homes and other protected places. Data centers can still be approved, but these rules add construction, compliance, or review costs.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Gratz Borough
The rules are in Ordinance 4826, which Borough Council adopted on April 8, 2026.Gratz Borough, Dauphin County — data-center ordinance (No. 4826)

What this means

The measure imposes noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements19
  • Conditional use, § 502 and § 602.28.J(3); no approval expiration

  • Up to 110 ft with added setback above 40 ft, § 602.28.A

  • 65 dBA day and 55 dBA night, § 602.28.G(3)

  • Baseline study only; no background cap

  • Pre-construction baseline and projected study, and post-construction study within 12 months, § 602.28.G

  • Water feasibility study by a Borough-chosen firm for on-site sources, with well protection; no bar on wells for cooling, § 602.28.I

  • Quarterly third-party water use reporting; no drought plan, § 602.28.I(7)

  • Water from non-public sources must be treated to DEP industrial cooling water standards before discharge; no approved discharge plan, § 602.28.I

  • Energy generation stations must meet air-quality regulations, § 602.28.H

  • Cooling systems must avoid thermal discharge onto cropland in the overlay, § 602.28.J(5)

  • Positive interconnection study from the power provider; no electrical inspection, § 602.28.E.

  • Natural gas or renewable energy stations allowed by conditional use; coal and oil barred; no separate setbacks, § 602.28.H

  • Bond covers water infrastructure only; grid upgrades not addressed

  • Tree line buffer along buildings adjoining residential property and screening in the overlay; no width, § 602.28.A and J(7)

  • Evergreens, fencing, and berms required in the overlay to reduce visual, noise, and light impacts, § 602.28.J(7)

  • Emergency response plan prepared with the fire department and EMS, § 602.28.F

  • Fuel storage must meet state and federal standards only, § 602.28.C

  • Quarterly reports confirming water use, § 602.28.I(7)

  • Section 602.28.I(5) requires the water feasibility study to be conducted by a qualified firm chosen by the Borough at the applicant's sole cost, but this is a Borough-directed study of one topic rather than applicant-paid consultant review of the applicant's studies in land development review.

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the I-1 Industrial District and the Industrial-Agricultural Data Center Overlay District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data