Graham Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Graham Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Graham TownshipDraft Ordinance No. 2026-02 was advertised on October 15, 2026, and the Board of Supervisors plans to consider adoption at its November 9, 2026 meeting.Graham Township, Clearfield County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements28
Stand-alone township ordinance with no zoning districts; location not limited
Plans processed as land development under the subdivision ordinance; no conditional use or special exception, § 301
Section 302(5) caps Data Centers and accessory structures at 35 feet inclusive of roof-mounted equipment, but this standalone ordinance contains no district height limit for other principal buildings to compare.
Environmental impact assessment covering riparian buffers, streams, wetlands, and steep slopes, §§ 311-312
57 dBA weekday daytime and 47 dBA nights and weekends at the property line, above the 50 and 45 dBA standard, § 309(1)
Sound study must evaluate low-frequency ranges; no dBC limit, § 309(1)
Section 309(1)(a) to (c) require a preliminary study in land development, an interim study at building permit, and an as-built study six months after occupancy, using ANSI S1.4 meters, but the as-built study is not required to be taken at full operating load.
Generator testing weekdays 9:00 a.m. to 3:00 p.m.; no hours cap, § 313(5)(b)
Vibration study showing nothing perceptible beyond the property line, § 309(3).
Water feasibility study for nonpublic sources with drought modeling; no pump test or well ban, § 310(2)
Water uses for cooling disclosed and reuse, recycling, or alternative cooling required; closed loop not required, § 310(2)(c), (5)
Projected water demand and drought-scenario safe yield disclosed; no cap or ongoing reporting, § 310(2)(a), (d)
Adequate disposal of domestic and cooling wastewater must be shown, § 310(6)
Subdivision and land development standards incorporated and stormwater statement required, §§ 301(2), 312(1)(c)
Decommissioning plan covers removal of electronic equipment, batteries, and cooling equipment; no recycling, § 315(1)
Utility confirmation of capacity with the application and Board finding before approval; no third-party inspection, § 313(2), (7).
Energy generation supplying the data center must meet this ordinance, § 313(3)(a)
Substations screened by 10 ft landscaping or walls and placed at the side or rear; on-site lines of 34.5 kV and below buried, § 313(1)
500 ft landscape buffer next to residential buildings and sensitive receptors, § 303(1).
Acoustical screening and full enclosure of equipment within 1,000 ft of roads and homes; no 12 ft standard, § 304(1)-(2)
Emergency plan accepted by the fire department, annual inspections, and 24-hour contact signs; no annual plan update or radio coverage, § 314
Responder training required, but funding not assigned, § 314(1)(e), (3)
Annual fire safety inspections; no third-party electrical inspection, § 314(1)(f)
Impact analysis describes vehicle trips; no traffic impact study, § 311(1)(a)
110% security and immediate closure notice, but 12 months allowed for removal, § 315(2)-(4)
Section 203 defines a Data Center to include artificial intelligence and cryptocurrency mining, and excludes computers secondary to another permitted use such as office servers, but that exclusion states no size or power threshold.
Post-commissioning well testing plan; no ongoing noise, water use, or power reports, § 310(2)(j)
Section 313(7) allows suspension or revocation of approvals for failure to follow approved mitigation, and Section 506 provides civil remedies and per-day judgments, but no notice or hearing is required before revocation.
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data