Girard Township
Anti-Data Center Policies
Girard Township’s enacted ordinance requires separation from homes and other protected places, noise limits and testing, and money set aside for eventual removal. Approval remains possible, but these limits narrow where and how data centers can operate.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Girard TownshipThe Board of Supervisors enacted Ordinance No. 26-01, the Girard Township Data Center Ordinance, on October 13, 2026, and it takes effect five days after enactment.Girard Township, Erie County — data-center ordinance (No. 26-01)
What this means
The measure imposes setbacks from homes or other protected places, noise limits and sound testing and money set aside for eventual removal. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements25
Section 5.A caps Data Centers and accessory uses at 40 feet inclusive of roof-mounted equipment, but the I-2 district height limit for other principal buildings is not in the ordinance text.
New sound study for added accessory uses only; no new approval, Section 9.F
Sustained 67 dBA day and 57 dBA night at the property line and 57 dBA at residential and sensitive receptor lot lines, Section 9.A and D
Section 9.A requires preliminary, interim, and as-built sound studies using ANSI S1.4 meters, but the as-built study is not required to be taken at full operating load.
Generator noise evaluated; no testing limits, Section 9.B
Vibration study showing none perceptible beyond the property line, Section 9.C.
Hydrologist's feasibility study with flow and recovery testing of wells within 2,640 ft for nonpublic sources; no bar on wells where public water is available, Section 11.B
Closed-loop cooling encouraged only, Section 11.C
Quarterly water usage reports; no drought response plan, Section 11.B(15)
Section 11.E requires the applicant to show that disposal of domestic, cooling, and industrial wastewater has been provided for and approved by the Sewage Enforcement Officer or DEP, but the approval is not required before the zoning permit.
Removal of hazardous materials, cabling, and electrical components at decommissioning; no recycling plan, Section 18.A and C
Utility interconnection agreement certifying capacity; no electrical inspection, Section 12.A.
Generation for normal operations is a separate use with a separate permit, Section 12.B.
Known impacts on electric rates must be noted; no cost assignment, Section 12.A
Planted landscape buffer with tree and shrub standards; no width stated, Section 7
Equipment within 40 ft of roads or 60 ft of residential lot lines enclosed or screened; no 12-ft or acoustic standard, Section 8.A
Emergency Response Plan accepted by fire and emergency services; no annual update, radio coverage, or posted contacts, Section 13.A
Plan must ensure responder training; no funding, Section 13.A(4)
Hazardous materials removal addressed in decommissioning; no storage setbacks or containment, Section 18.C
Annual fire safety inspections with local fire services present, Section 13.A(5)
Construction transportation plan with road bond and repair duty; no work hours, Section 17
150% security, but removal within 18 months after decommissioning begins and no closure notice, Section 18.B, G, and J
Sound studies at least every three years and quarterly water usage reports, Sections 9.A and 11.B(15)
Noise violation is a violation of the ordinance; no specific penalties, Section 9.A(3)
Third-party sound assessor and applicant pays Township review of decommissioning estimates; no general expert review of studies, Sections 9.A and 18.I
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Special exception in the I-2 Industrial District