Freeport Township

Anti-Data Center Policies

Freeport Township’s enacted ordinance requires setbacks, minimum site sizes, noise limits, and sound testing, substantially restricting potential sites and project designs while leaving an approval route available.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Freeport Township
The standards were set by Ordinance No. 01-2026, which the Board of Supervisors adopted on July 27, 2026, the same day it adopted Ordinance No. 03-2026 amending the Noise and Dust Ordinance (Ordinance No. 01-2024).Freeport Township, Greene County — data-center ordinance (No. 01-2026)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and noise limits and sound testing. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.

Restrictions & requirementsHide restrictions & requirements30
  • Each data center building limited to 125,000 gross sq ft, Ord. 01-2026 § 3.B(15).

  • Ordinance 01-2026 Section 3.B(2) bars Data Center buildings, Data Center Accessory Uses, and Data Center Equipment within 1,500 feet of any occupied residential structure, measured radially from each of them.

  • Environmental Impact Assessment required before construction, Ord. 01-2026 § 3.B(34)

  • 55 dBA day and 45 dBA night at the property line nearest a residential receptor, applied by Ord. 01-2026 § 3.B(23), Ord. 03-2026 § 6.A-B

  • Ordinance 03-2026 Section 6.C caps noise at 10 dBA above ambient and Sections 6.H and 6.I require a 72-hour ambient baseline and bar continuous mechanical noise above it, but the baseline is not an L90 measure and the absolute limits govern when more restrictive, so no floor applies.

  • Octave band limits of 65 dB at 31.5 Hz and 60 dB at 63 Hz with 1/3 octave analysis; no dBC day and night limits, Ord. 03-2026 § 6.E

  • Noise study with the application, 72-hour ambient baseline, and post-construction study before occupancy; none at building permit, § 3.A(3), Ord. 01-2026 § 3.B(22), and Ord. 03-2026 § 6.H

  • Non-outage generator use weekdays 8 a.m. to 8 p.m., with a 120-hour annual maintenance cap, and routine testing must meet the noise limits, Ord. 01-2026 § 3.B(8) and (37) and Ord. 03-2026 § 8.N

  • Water feasibility study for nonpublic sources, including effects on nearby wells, Ord. 01-2026 § 3.B(10)

  • Closed-loop systems required as a water conservation measure; evaporative cooling not restricted, Ord. 01-2026 § 3.B(33)

  • Projected water demands disclosed; no cap, reporting, or drought plan, Ord. 01-2026 § 3.B(9)-(10)

  • Ordinance 01-2026 Section 3.B(11) requires the operator to show that disposal of cooling and industrial wastewater has been provided for and approved by PA DEP, with chemicals listed, but does not make that approval a condition before the zoning permit.

  • EPA Tier 4 final generators required; annual reports cover generator hours, not emissions, Ord. 01-2026 § 3.B(32) and (37)(d)

  • Decommissioned hardware recycled through certified e-waste facilities; no plan for batteries and refrigerants, Ord. 01-2026 § 3.B(46)(b)

  • Utility letter certifying grid capacity and the executed utility agreement; no third-party electrical inspection, Ord. 01-2026 § 3.B(5).

  • Power lines buried except at switchyards and substations; substations not screened or placed, Ord. 01-2026 § 3.B(29)

  • Utility letter must state the potential impact on the electric grid; cost of upgrades not assigned, Ord. 01-2026 § 3.B(5)

  • Planted landscape buffer of at least 100 ft next to residential, commercial, and agricultural areas, Ord. 01-2026 § 3.B(26).

  • Durable building materials required; no facade standards, Ord. 01-2026 § 3.B(14)

  • Equipment near roads, homes, or sensitive receptors enclosed or fully screened, placed to shield noise; no 12-ft standard, Ord. 01-2026 § 3.B(22)(a)-(b) and (24)

  • Architect's renderings with elevations required, § 3.A(1)

  • Plan reviewed by the fire department and reviewed at an annual public safety meeting; no radio coverage or posted 24-hour contact, Ord. 01-2026 § 3.B(41)-(42)

  • Ordinance 01-2026 Section 3.B(13) requires annual responder training by the operator and special firefighting equipment supplied to the fire companies at the operator's expense, but it does not require training before occupancy or the equipment to be kept on site.

  • Wastewater chemicals listed and hazardous leaks reported; no storage setbacks or spill containment, Ord. 01-2026 § 3.B(11) and (39)

  • Annual fire safety inspections; no third-party electrical inspection before occupancy, Ord. 01-2026 § 3.B(41)(e)

  • Construction truck routes, road maintenance agreement, and road bond; no construction hours, Ord. 01-2026 § 3.B(16)-(18)

  • 125% security posted before construction; no removal deadline after abandonment, Ord. 01-2026 § 3.B(45)-(46)

  • Continuous real-time sound monitoring accessible to the Township for continuous mechanical noise, plus annual reports on generator hours and complaints, Ord. 03-2026 § 6.F and Ord. 01-2026 § 3.B(37)(d) and (43)

  • Ordinance 01-2026 Section 5 provides civil penalties up to $1,000 per day and lets the Township suspend or revoke the Use Permit for continued noncompliance, but no notice and hearing are required before revocation.

  • Studies and sound measurements at the owner's expense, with a Township-approved acoustical professional after complaints; review of applicant studies not assigned, § 3.A(5) and Ord. 03-2026 § 6.J and 11

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data