Franklin Township’s enacted ordinance limits noise and building height, requires sound testing, and sets setbacks from homes and other protected places; data centers may still be approved, but compliance can add costs.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Franklin TownshipThe rules are in Section 419A, added by Ordinance No. 2026-2, which the Supervisors adopted on June 10, 2026, and the Planning Commission is working on a low-frequency noise and infrasound amendment.Franklin Township, York County — data-center ordinance (No. 2026-2)
What this means
The measure imposes noise limits and sound testing, setbacks from homes or other protected places and building-height limits. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements27
Environmental Impact Assessment covering riparian buffers, streams, and wetlands, Section 419A.K
57 dBA day and 47 dBA night at the property line, Section 419A.H.1
Sound study must evaluate low-frequency ranges; no dBC limit, Section 419A.H.1
Section 419A.H.1.a to c requires preliminary, interim, and as-built sound studies using ANSI S1.4 sound level meters, with the as-built study six months after the certificate of occupancy, but the limits apply to normal operations and no study is required at full operating load.
Vibration study showing no perceptible vibration beyond the property line, Section 419A.H.
Must be served exclusively by public water, so wells may not be used, Section 419A.I.1
Water use for cooling must be described and conservation or alternative cooling used, Section 419A.I.2 and I.3
Projected water demand disclosed; no cap or reporting, Section 419A.I.3
Adequate disposal of cooling wastewater must be shown, Section 419A.I
Air quality permits, if required, in place before occupancy, Section 419A.L.4.e
Decommissioning plan removes electronic equipment and batteries; recycling not required, Section 419A.N.2
Utility capacity certification with the application; no electrical inspection, Section 419A.L.2.
Energy generation feasibility report and solar ready design only, Section 419A.L.3
Generation supplying the data center must meet the ordinance as a principal use, Section 419A.L.3.a.
Substations screened by a 10 ft wall or landscaping, placed at the side or rear, and lines of 34.5 kV or less buried, Section 419A.L.1
Required upgrades and rate impacts disclosed and mitigated to the Board's satisfaction; payment not assigned, Section 419A.L.2
200 ft landscape buffer next to residential uses, Section 419A.C.1.
Acoustical screening of rooftop equipment and enclosure or screening within 500 ft; no 12 ft height, Section 419A.D
Emergency Response Plan accepted by the fire department and 24-hour contact signs; no annual updates or radio coverage, Section 419A.M
First responders must receive system-specific training; funding not assigned, Section 419A.M.1.e
Double-walled fuel storage with leak detection; no storage setbacks, Section 419A.L.4.d
Annual fire safety inspections; no third-party electrical inspection, Section 419A.M.1.f
Vehicle trips described in the impact analysis; no traffic study, Section 419A.J
Section 1 defines a data center to include artificial intelligence, cryptocurrency mining, blockchain processing, and server farms, and excludes equipment customarily incidental to another permitted use, such as office servers, but sets no size or power threshold for that exclusion.
One as-built sound study after occupancy, Section 419A.H.1.c
Section 419A.L.5 states that failure to comply with approved mitigation measures is a violation that may result in suspension or revocation of approvals or permits, but provides no notice and hearing procedure and does not cite Sections 616.1 or 617.2 of the Municipalities Planning Code.
Owner pays the Township Engineer's review of decommissioning estimates only, Section 419A.N.3
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the Industrial Zone
Sources
- franklintownship.org
- franklintownship.org
- franklintownship.org
- franklintownship.org
- franklintownship.org
- franklintownship.org
- franklintownship.org
- franklintownship.org
- franklintownship.org
- franklintownship.org
- franklintownship.org
- franklintownship.org
- franklintownship.org
- franklintownship.org
- franklintownship.org
- www.ycpc.org
- padatacenterordinances.org
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data