Franklin Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Franklin Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Franklin TownshipThe proposal is still before the Planning Commission, which is reviewing public comments and expects the revised proposal to return to Adams County for review, and no adoption hearing has been scheduled.Franklin Township, Adams County — proposed data-center ordinance (None Adopted)
What this means
The proposal would provide a route for data centers through a special permit or conditional-use review in designated districts. That offers legal certainty, but the extra approval step can add time and uncertainty.
Restrictions & requirementsHide restrictions & requirements20
200-ft setback for loading areas only; 50-ft buffer, § 175-64
55 dBA day and 45 dBA night, § 175-64
Section 175-64 bars sound more than 10 dBA above pre-development ambient, with 55 dBA day and 45 dBA night maximums at the property line, but the ambient is not defined as L90, no method for measuring it is stated, and no floor is set below which the cap does not apply.
Octave-band frequency analysis; no dBC limit, § 175-64
Section 175-64 requires preliminary (before preliminary approval), interim (building permit), and as-built studies six months after occupancy using ANSI S1.4-2014 meters and ANSI S1.11 frequency analysis, but compliance is shown under typical operating conditions and the as-built study is not required at full operating load.
Vibration study showing none past the property line, § 175-64.
Pump-tested well study; no cooling-well bar, § 175-64
Continuous monitoring with annual plan; no cap or drought plan, § 175-64
Cooling wastewater disposal approved by the SEO or DEP as part of the application, § 175-64
Utility approval of service application, § 175-64.
Substations part of the use and screened, § 175-64
50-ft buffer beyond setback, § 175-64
Fully shielded with a property-line limit, § 175-64
Equipment screened, § 175-64
Plan reviewed by fire department; no updates, radio, or contacts, § 175-64
Tank setbacks with spill containment, § 175-64.
Annual fire safety inspections, § 175-64
Section 175-64 requires a traffic impact study in every case addressing daily operational traffic and emergency response access, but it does not cover construction traffic or set a study area reaching the nearest arterial or interchange.
Agreement and security with no amount; 12-month removal, § 175-64 (redline)
Annual water monitoring plan, § 175-64 (redline)
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: special exception in the Industrial zone
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data