Foster Township

Anti-Data Center Policies

Foster Township confines data centers to a designated overlay, requires at least 110 acres, and requires conditional-use approval, substantially limiting eligible sites. A reported noise-limit typo is not treated as a reliably enforceable restriction.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Foster Township
The rules are in Ordinance No. 2026-01, which the Board of Supervisors enacted on July 1, 2026, after public hearings, adding Chapter 13 to the township zoning ordinance and mapping the overlay on the zoning map.Foster Township, Schuylkill County — data-center ordinance (No. 2026-01)

What this means

The ordinance confines data centers to an overlay and requires at least 110 acres plus conditional-use approval. That significantly limits feasible sites; the reported noise-limit typo is not treated as a reliably enforceable extra restriction.

Restrictions & requirementsHide restrictions & requirements19
  • Sections 301.7 and 1301 permit data centers by conditional use in the D-C Data Center Overlay, which is drawn on the adopted Zoning Map, but the text does not expressly exclude data centers from all other districts.

  • Printed limits of 7 dBA weekday daytime, an apparent typographical error, and 77 dBA night and weekend at the property line, Section 1305.1

  • Section 1305.1 requires a preliminary study in the conditional use process, an interim study at building permit, and an as-built study six months after occupancy, using ANSI S1.4 meters and generally accepted methodology.

  • Generator testing not limited; noise limits do not apply during power outages, Section 1305.2

  • Vibration study showing no vibration perceptible beyond the property line, Section 1305.3.

  • Public water certification, or a water feasibility study with safe yield and nearby wells for nonpublic sources; no pump tests or limit on wells, Section 1306.1 and 1306.2

  • Projected water demands disclosed in the feasibility study for nonpublic sources, Section 1306.2.a

  • Section 1306.4 requires a showing that disposal of domestic and cooling wastewater has been provided and approved by the SEO or DEP, without stating when the approval must be in hand.

  • Electric provider must certify capacity and service; no third-party electrical inspection, Section 1307.1.

  • Substations counted as accessory uses, and power supply equipment within 300 ft must be enclosed or screened, Section 202 and Section 1304.1

  • Known impacts on electric rates or availability must be noted, Section 1307.1

  • 25-ft landscape buffer, Section 1303.1

  • Full cutoff fixtures projecting light below the horizontal; no limit on light crossing the property line, Section 1311

  • Equipment within 300 ft of roads, residential districts, or sensitive receptors enclosed or screened; no height or acoustic standard, Section 1304.1

  • Emergency Response Plan reviewed and accepted by the local fire department; no annual updates, radio coverage, or posted contacts, Section 1308.1

  • Emergency Response Plan must ensure first responders receive system-specific training, Section 1308.1.d

  • Annual fire safety inspections by a qualified professional, Section 1308.1.e

  • One as-built sound study after occupancy, with later studies at township request, Section 1305.1.c

  • As-built noise violation treated as a violation of the ordinance, Section 1305.1.c

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the D-C Data Center Overlay District