Findlay Township

Anti-Data Center Policies

Findlay Township’s enacted ordinance requires removal funds, noise limits and sound testing, and setbacks from homes and other protected places. Data centers may still be approved, but these rules add costs and review requirements.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Findlay Township
The rules are in Ordinance No. 469, which the Board of Supervisors adopted on June 10, 2026, after a public hearing, amending the township zoning ordinance.Findlay Township, Allegheny County — data-center ordinance (No. 469)

What this means

The measure imposes money set aside for eventual removal, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements23
  • 67 dBA weekday daytime and 57 dBA night and weekend at the property line, § 117.604.78.5.A

  • Section 117.604.78.5.B requires a preliminary study in the conditional use process, an interim study at building permit, and an as-built study within six months of occupancy, using ANSI S1.4 meters and generally accepted methodology.

  • Generator testing hours not addressed; noise limits do not apply during power outages, § 117.604.78.5.C

  • Vibration study showing no vibration perceptible beyond the property line, § 117.604.78.5.D.

  • Public water from the Findlay Township Municipal Authority required with a supply certification; wells and pump tests not addressed, § 117.604.78.7.A

  • Wastewater disposal, including cooling and industrial wastewater, must be provided and approved by the Municipal Authority as part of the conditional use, § 117.604.78.7.B

  • Decommissioning requires removal of servers, computer equipment, and hazardous substances; no recycling plan, § 117.315.B

  • Electric provider must certify capacity and service; no third-party electrical inspection, § 117.604.78.8.A.

  • Substations counted as data center accessory uses, and power supply equipment within 300 ft must be enclosed or screened, § 117.202 and § 117.604.78.4

  • Battery storage must meet the township battery energy storage system section, § 117.604.78.9.B

  • Known impacts on electric rates or availability must be noted, § 117.604.78.8.A

  • 25-ft landscape buffer with 75% evergreen native plantings, § 117.604.78.3

  • Photometric plan required; shielding not addressed, § 117.604.78.6

  • Equipment within 300 ft of streets, protected districts, or sensitive receptors fully enclosed or screened; no height or acoustic standard, § 117.604.78.4

  • Emergency Response Plan reviewed and accepted by the Imperial Volunteer Fire Department; no annual updates, radio coverage, or posted contacts, § 117.604.78.9.A

  • Emergency Response Plan must ensure first responders receive system-specific training, § 117.604.78.9.A(4)

  • Hazardous substances addressed only at decommissioning, § 117.315.B

  • Annual fire safety inspections by a qualified professional, § 117.604.78.9.A(5)

  • 110% financial security, immediate notice of cessation, and removal within 12 months, § 117.315.B and D

  • Section 117.315.C and D require the decommissioning estimate to be updated after the first year of occupancy and every fifth year, and require the security to be reset at each interval to 110 percent of the updated estimate.

  • One as-built sound study after occupancy, § 117.604.78.5.B(3)

  • As-built noise violation treated as a violation of the ordinance, § 117.604.78.5.B(3)

  • Section 117.604.78.5.A requires the sound study to be prepared by an acoustical expert selected jointly by the Township and applicant at the applicant's sole cost, as part of the conditional use process.

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the LI and HI districts

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data