Ferguson Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Ferguson Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Ferguson Township
The Planning Commission's October 26, 2026 agenda listed the revised draft with a recommended motion to recommend approval to the Board of Supervisors, and the outcome of that meeting and any Board of Supervisors hearing date had not been posted as of October 29, 2026.Ferguson Township, Centre County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements23
  • Section 27-740.3.B bars any data center building, structure, or associated mechanical equipment, including generators, cooling systems, substations, and rooftop or ground-mounted equipment, within 1,000 ft of any lot with a residential use or zoned residential (October 22, 2026 draft).

  • Environmental and community impact analysis required, § 27-502.37.B.2

  • 55 dBA day and 50 dBA night at residential boundaries, § 10-309.3

  • dBC may not exceed concurrent dBA by more than 10 dB, § 10-309.4

  • Ambient study and sound modeling with application, post-construction study; none at building permit, § 27-740.5.D-F

  • Generators limited to backup and testing of 2 hours per session, § 10-308.13

  • ISO 2631-2 and 200 µm/s limit at neighboring foundation, with study, § 27-740.5.G-H.

  • Public water capacity letter required; groundwater wells, springs, and surface withdrawals barred, § 27-740.6.A

  • Section 27-740.6.B allows discharge only to public sewer with written UAJA approval, a capacity letter, and proof of a discharge permit, but the text does not say the approvals must be in hand before the zoning permit.

  • PA DEP confirmation of Air Quality Permit application or exemption; no Tier 4, § 27-740.10

  • Electronic Waste Plan for servers and batteries; refrigerants not named, § 27-740.7

  • Utility capacity confirmation; no third-party electrical inspection, § 27-740.9.A.

  • Substations within the 1,000-ft setback rule and equipment shielded by the building; lines not buried, § 27-740.3.B and D

  • 50-ft landscape buffer next to residential uses and districts, § 27-740.3.E

  • Landscape, fence, or wall screening and natural sound barriers; no height standard, § 27-502.37.C.3 and § 27-740.5.B

  • Preliminary elevations and site plans required, § 27-502.37.B.2.c

  • Plan reviewed by fire department, radio coverage, 24-hour signage; no annual update, § 27-740.12

  • Plan must include first responder training requirements; no funding, § 27-740.12.E

  • Hazardous waste permits and EPA ID; no storage setbacks or containment, § 27-740.8

  • Annual fire safety inspections, § 27-740.12.E.7

  • Decommissioning plan and bond; no 110%, notice, or 6-month removal rule, § 27-502.37.C.5

  • One post-construction noise study, with later as-built studies optional, § 27-740.5.E

  • Section 27-740.5.H reserves an independent third-party review of any study at the applicant's expense, and the studies are filed with the conditional use application, so the review is not tied to land development review.

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the Industrial and IRD districts (large and hyperscale in Industrial only)

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data