Fell Township
Anti-Data Center Policies
Fell Township requires data centers to maintain setbacks from homes and other protected places, meet noise limits, and undergo sound testing. Approval remains possible, but these restrictions significantly limit suitable sites and operations.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Fell TownshipThe rules were set by Ordinance No. 04062026-1, which the Board of Supervisors adopted and signed on April 6, 2026, effective immediately.Fell Township, Lackawanna County — data-center ordinance (No. 04062026-1)
What this means
The measure imposes setbacks from homes or other protected places and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements19
Section 505.jA caps Data Centers and accessory uses at 40 feet inclusive of roof-mounted equipment, but the district height limit for other principal buildings is not in the amending text.
65 dBA weekday daytime and 55 dBA at night and weekends at the property line, § 505.jC
Section 505.jC(i) to (iii) require preliminary, interim, and as-built sound studies using ANSI S1.4 meters, but the as-built study is not required to be taken at full operating load.
Generator testing on weekdays 9:00 a.m. to 5:00 p.m. only; no hours cap, § 505.jC
Water feasibility study for nonpublic sources; no pump tests or well limits, § 505.jE
Water used for cooling must be disclosed in the feasibility study, § 505.jE(iii)
Projected water demand disclosed; no cap, reporting, or drought plan, § 505.jE(i)
Section 505.jF requires the applicant to show that disposal of domestic, cooling, and industrial wastewater has been provided for and approved by the Township, SEO, LRBSA, or DEP, but the approval is not required before the zoning permit.
Generator emissions must meet federal and state rules with proof of permits, § 505.j (generator paragraph)
Utility certification of capacity and service; no electrical inspection, § 505.jG.
Known impacts on electric rates must be noted, § 505.jG
Screening and buffering under § 414; no 100-ft width, § 505.jB
Data center and accessory uses completely enclosed by screening; no height or acoustic standard, § 505.jB
Emergency Response Plan accepted by the fire department; no annual updates, radio coverage, or contacts, § 505.jH
First responders must receive training, § 505.jH(iv)
Fuel storage must meet applicable rules only, § 505.j (generator paragraph)
Annual fire safety inspections; no third-party electrical inspection, § 505.jH(v)
One as-built sound study after occupancy, § 505.jC(iii)
Noise violation treated as a violation of the Zoning Ordinance, § 505.jC(iii)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the M-1 District
Sources