Fayette Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Fayette Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Fayette TownshipProposed Ordinance No. 4 of 2026 was advertised on September 16, 2026 for consideration at the October 14, 2026 meeting, and the township secretary wrote on October 19, 2026 that the Supervisors will adopt it at their November 11, 2026 meeting.Fayette Township, Juniata County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose money set aside for eventual removal, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements28
Permitted only in Industrial zones and, with approval, Commercial zones; prohibited elsewhere, Section 2.B(1).
Permitted by right in Industrial zones; special exception or conditional use only in Commercial zones, Section 2.B(1)
100 ft from all property lines; 100-ft buffer yard along lines within 500 ft of Sensitive Receptors, Section 2.E(1) and Q(3)
35-ft height limit, but screened rooftop equipment may exceed it, Section 2.D and Q(2)(ii)(3)
Riparian forest buffer of 100 ft on each side, wider on slopes and 25 ft more at wetlands, Section 2.AA(6)-(8)
Single 24-hour CNEL limit of 60 dBA at Sensitive Receptor property lines, Section 2.H(1)
Developer must show dBC and octave band levels are acceptable; no numeric limit, Section 2.H(1)(v)
Pre-construction study with the application and post-construction study before occupancy, Section 2.H(4)
Water feasibility study; private wells require a hydrogeologic study with pumping tests; wells not barred where public water exists, Section 2.S
Cooling method not required to be disclosed or restricted; reclaimed water only encouraged, Section 2.K(3) and W
Peak water demand calculated in the water study; no cap or reporting, Section 2.S(2)-(3)
Impact analysis covers sewage disposal and wastewater; no cooling discharge plan, Section 2.R(4)-(5)
Emission sources identified with best management practices; no generator emission standard, Section 2.R(6)
Decommissioning plan removes electronic equipment and batteries with certified e-waste recycling; refrigerants not named, Section 2.V
Utility capacity letter and third-party electrical inspection before occupancy, not before approval, Section 2.K
Substations screened 10 ft and placed at side or rear; on-site lines of 34.5 kV and below buried, Section 2.N
Buffer yard of 100 ft or more along lines within 500 ft of Sensitive Receptors, including homes, Section 2.Q(3).
Full cutoff fixtures with a 0.1 footcandle limit at homes, Section 2.L
Ground and rooftop equipment fully screened; no 12-ft or acoustic standard, Section 2.Q(2)
Line-of-sight study for service area screening; no visual impact study with renderings, Section 2.Q(1)
Emergency Response Plan reviewed by the fire department, radio coverage, and 24-hour contact sign; no annual plan updates, Section 2.O and U
First responders must receive system-specific training; funding not assigned, Section 2.U(1)(v)
Section 2.U(1)(vi) requires the emergency response plan to provide for annual fire safety inspections by a qualified professional on behalf of the data center, and Section 2.K(7) requires a third-party electrical inspection before occupancy, but no report to the municipal fire official or deadline for correcting deficiencies is required.
Vehicle trips described only; no traffic study, Section 2.R(1)
110% financial security, but no closure notice or removal deadline, Section 2.V
Post-construction sound study before occupancy; later studies optional, Section 2.H(4)(iii)
Owner must remediate sound violations; no specific penalties, Section 2.H(4)(iii)
Township-selected engineer reviews sound studies; cost not assigned, Section 2.H(4)(i)
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: permitted by right in Industrial zones, special exception or conditional use in Commercial zones
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data