Falls Township

Anti-Data Center Policies

Falls Township’s enacted measure gives local officials a protected period to address zoning gaps, which can delay developers challenging existing rules but does not ban every data-center project.

Incentives

Financial Incentive
2

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Falls Township
The supervisors approved Resolution 2026-11 by a 3-0 vote, declaring parts of Chapter 209 Zoning substantively invalid and starting a 180-day curative amendment period.Falls Township, Bucks County — data-center resolution 2026-11

What this means

The measure starts a protected period for local officials to fix gaps in their zoning rules. This can delay developers who need to challenge the old rules, but it does not by itself prohibit every data-center project.

Sources

pending · Falls Township
The draft (version 3, Ordinance No. left blank) was posted on October 30, 2026 for public review through November 23, 2026 under Resolution 2026-11, with Board discussion planned for November 23, 2026, advertisement in December 2026, and adoption expected in early 2027.Falls Township, Bucks County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.

Restrictions & requirementsHide restrictions & requirements32
  • Conditional use under § 209-50; no lapse period stated for data center approvals, Section 1

  • Height cap only; no footprint, megawatt, or coverage cap, § 209-94.A

  • 2,000 ft from residential district lines and residential property lines, measured from any part containing servers, power generation, substations, mechanical systems, or noise-generating equipment, § 209-94.C

  • 80 ft including rooftop equipment and accessory uses, § 209-94.A; not tied to the MPM district limit for other principal buildings

  • Environmental Impact Study of wildlife habitats and scenic areas with mitigation and annual reporting; no riparian buffer, § 209-94.J

  • Changes in cooling technology or capacity require an amended thermal plan, and flow or discharge changes require approval; no general expansion trigger, § 209-94.I(9) and U

  • 60 dBA day and 55 dBA night Leq at property lines abutting residential districts, above the 50 and 45 dBA standard, § 209-94.H(6), Table 1

  • Octave-band limits at 31.5, 63, and 125 Hz (65/60, 60/55, 55/50 dBZ day/night) at residential boundaries, § 209-94.H(7), Table 2

  • Pre-construction study with octave-band analysis and post-construction study 1 to 12 months after occupancy; full operating load and a noise measurement method are not stated, § 209-94.H(1)-(3)

  • Generator placement and reduced runtime only; no testing hours or cap, § 209-94.H(9) and Z

  • 0.02 in/s PPV at property lines and 50 VdB at residential property lines, with studies under the FTA Detailed Vibration Analysis guidelines, § 209-94.H(1)-(2), (8)

  • Closed-loop cooling required with net zero potable water draw for cooling, § 209-94.M-N

  • Annual water consumption report; no drought plan, § 209-94.N

  • Wastewater Discharge Plan with treatment capacity confirmation for approval; approvals not required before the zoning permit, § 209-94.P-S

  • Generators must meet or exceed Tier 4 standards, with annual reports on emissions output, § 209-94.Z and JJ

  • Thermal Impact Mitigation Plan evaluating off-site thermal impacts at property boundaries under seasonal conditions and evaluating waste heat reuse, § 209-94.I(2), (4)

  • Electronic Waste Plan for servers, hazardous materials, and batteries; refrigerants and a disposal contract not required, § 209-94.HH

  • Renewable power efforts documented before occupancy and annually, and a green building or energy management certification maintained; no energy plan with peak demand, § 209-94.G and V

  • On-site generation addressed through grid export limits and a required clean air microgrid or CHP system; not a separate use with its own approval, § 209-94.W and Z

  • Substations counted as accessory uses and kept 2,000 ft from residential lines; no screening or burial of lines, § 209-93 and § 209-94.C

  • 100-ft deciduous and evergreen planted buffer next to residential districts and uses, maintained; replacement of dead plants not stated, § 209-94.D

  • Township lighting standards apply; no shielding requirement in the text, § 209-94.F

  • Rooftop equipment screened by a parapet sound wall; ground equipment screening not addressed, § 209-94.E

  • Scenic areas evaluated in the environmental study; no visual study or elevations, § 209-94.J

  • Emergency Response Plan acceptable to the fire department and EMS before building permits, with 24-hour contact signage and radio coverage; no annual update or walk-through, § 209-94.DD-GG

  • Disposal of hazardous materials in the waste plan only; no storage setbacks or containment, § 209-94.HH

  • Annual fire safety inspections by a qualified professional; no report to the fire official or correction period, § 209-94.EE(5)

  • Traffic Impact Study for construction and operation under PennDOT standards; study area to the nearest arterial or interchange not stated, § 209-94.AA

  • Decommissioning plan without financial security, § 209-94.II

  • Annual reports on energy consumption, emissions, and water intensity, § 209-94.JJ

  • Township and its consultants may require supplemental thermal plans; review cost not assigned to the applicant, § 209-94.I(8)

  • Owner and operator named on entrance signage only; no disclosure before approval, § 209-94.DD

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Not defined in zoning; curative amendment would add a conditional use in the MPM district

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data