Anti-Data Center Policies

Fairview Township requires data centers to meet minimum site sizes and keep set distances from homes and other protected places, increasing costs while still allowing approval.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Fairview Township
The rules are in Ordinance No. 2025-3, which the Board of Supervisors adopted on July 28, 2025.Fairview Township, York County — data-center ordinance (No. 2025-3)

What this means

The measure imposes setbacks from homes or other protected places and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements4
  • Pre- and post-construction sound studies, § 300-72E(7)

  • Utility approval of service application, § 300-72E(1).

  • Backup systems must meet fire codes, § 300-72E(2)

  • Equipment screened and placed away from homes, § 300-72E(7)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Commercial Business and Industrial Business districts

Sources