Borough of Exeter
Anti-Data Center Policies
Exeter Borough’s enacted rules require setbacks from homes and other protected places, noise limits and sound testing, and money set aside for eventual removal. Data centers can still seek approval, but these limits narrow where and how they can operate.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Exeter BoroughThe current rules are in Ordinance No. 5 of 2026, which Borough Council adopted on May 5, 2026.Exeter Borough, Luzerne County — data-center ordinance (No. 5 Of 2026)
What this means
The measure imposes setbacks from homes or other protected places, noise limits and sound testing and money set aside for eventual removal. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements24
Agricultural lands are only sensitive receptors for setbacks; no bar
Environmental Impact Statement required, Section 902.52.D.6
67 dBA day and 57 dBA night at the property line, Section 902.52.C.1
Section 902.52.C.1 requires preliminary, interim, and as-built sound studies using ANSI S1.4 sound level meters, with the as-built study six months after the certificate of occupancy, but the as-built study is not required at full operating load.
Backup generators may not run 8 p.m. to 8 a.m. except emergencies; no hours cap, Section 902.52.E.5
Vibration study showing none perceptible past the property line, Section 902.52.C.3.
Water feasibility study for non-public sources; no bar on wells for cooling, Section 902.52.D.3
Water use by purpose including cooling must be described; closed loop encouraged only, Section 902.52.D
Projected water demand disclosed, Section 902.52.D.3.a
Section 902.52.D.5 requires the applicant to demonstrate that adequate means of disposal for domestic wastewater and wastewater used for cooling or industrial purposes have been provided and approved by the Sewage Enforcement Officer and/or DEP.
Tier IV generators required; no annual emissions testing, Section 902.52.E.4
Decommissioning plan covers disposal and recycling; batteries and refrigerants disposed per law, Section 902.52.I
Utility certification of capacity; no electrical inspection, Section 902.52.E.1.
On-site generation for normal operations is a separate use with its own approval, Section 902.52.E.3.
All new electric lines underground; substations not separately screened or placed, Section 902.52.E.2
50-ft planted buffer, Section 902.52.A.4
Section 902.52.G.1 requires every facade facing a road or existing residential use to include at least two design elements every 150 horizontal feet, such as a change in material, pattern, texture, or color, a height change, or 5 ft step-backs, and Section 902.52.G.1.e requires a 20 ft long, 5 ft deep recess or offset for every 200 ft of facade.
Equipment within 300 ft enclosed or screened and rooftop equipment screened on all sides; no 12-ft height, Section 902.52.B and G.1.f
Emergency response plan accepted by the fire department; no annual update, radio, or contacts, Section 902.52.F.1
Plan must ensure responder training; no funding, Section 902.52.F.1.d
Annual fire safety inspections, Section 902.52.F.1.e
Decommissioning plan, start within 1 year and finish within 18 months; no financial security, Section 902.52.I
One as-built sound study after opening, Section 902.52.C.1.c
As-built noise exceedance is a violation; general enforcement only, Section 902.52.C.1.c
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the I-1 General Industrial District