Eldred Township
Anti-Data Center Policies
Eldred Township requires studies and utility checks, limits noise, requires sound testing, and sets setbacks from homes and other protected places. Data centers may still be approved, but meeting these requirements adds costs.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Eldred TownshipThe standards in new Section 812 of the zoning ordinance were set by Ordinance No. 2026-03, which the Board of Supervisors enacted by a 4 to 0 vote on September 16, 2026.Eldred Township, Monroe County — data-center ordinance (No. 2026-03)
What this means
The measure imposes technical studies and utility checks, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements23
Conditional use before the Board of Supervisors; no approval expiration, § 812A
200-foot setback from all other zoning districts and homes, § 812C(4)
200-foot setback from schools, day care, parks, and other sensitive receptors, § 812B and C(4)
60-foot height including rooftop equipment, § 812C(2)
Single limit set by the commercial maximum sound levels at the property line, § 812F(1)
Section 812.F(1) requires preliminary, interim, and as-built sound studies using ANSI S1.4 sound level meters, with the as-built study six months after the certificate of occupancy, but the as-built study is not required to be taken at full operating load.
Limits waived during outages; generator noise only reported, § 812F(2)
Vibration study showing none perceptible beyond the property line, § 812F(3).
Water feasibility study with pumping tests for nonpublic water; no bar on wells for cooling, § 812G(2)
Projected water demand and use by purpose, including cooling, disclosed, § 812G(2)
Nonpublic disposal of cooling wastewater must be approved by the sewage officer or DEP, § 812H(2)
Utility certification of capacity and service; no electrical inspection, § 812I(1).
On-site generation for normal operations is a separate use needing its own zoning approval, § 812I(2).
Power supply equipment within 300 feet of roads or homes enclosed or screened, § 812E(1)
Known impacts on electric rates must be noted; no cost assignment, § 812I(1)
25-foot planted buffer, § 812D(1)
Two facade design elements every 150 feet on facades facing roads or homes, § 812K.
Equipment within 300 feet of roads or homes enclosed or screened; 8-foot fence, § 812E
Emergency response plan reviewed by the fire department; no annual updates or radio coverage, § 812J(1)
Plan must ensure first responders are trained; no funding, § 812J(1)(d)
Annual fire safety inspections; no electrical inspection, § 812J(1)(e)
One as-built sound study after opening, more only on request, § 812F(1)(c)
Noise found by the as-built study is a violation; no specific penalty, § 812F(1)(c)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the I Industrial District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data