Easttown Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Easttown Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Easttown TownshipOn September 22, 2026, the Board of Supervisors voted 3 to 0 to send the draft to the township and county planning commissions, and the township Planning Commission is scheduled to review it on November 5, 2026.Easttown Township, Chester County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose noise limits and sound testing, setbacks from homes or other protected places and building-height limits. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements17
Must meet Chapter 278 noise limits, § 455-19.1.F(2)(b)
Full spectrum modeling of low-frequency noise required, § 455-19.1.F(2)(e)
Study with application and within 180 days of operation, § 455-19.1.F(1)-(2)
Section 455-19.1.F(2)(f) limits ground vibration to 0.02 inches per second peak particle velocity at or beyond the property line, measured under U.S. Bureau of Mines RI 8507, and below the human perception threshold of ISO 2631-1, with pre-construction and as-built vibration studies under Section 455-19.1.F(1) and (2).
Public water required; groundwater not a primary cooling source, § 455-19.1.G(1) and (4)
Section 455-19.1.G(5) requires air-cooled or closed-loop cooling and allows an alternative only if it is shown to use less water and energy than those systems, but does not expressly limit evaporative systems to a stated water-use rate or require them to be shown to meet the noise limits.
Water use estimates and drought response plan, § 455-19.1.G(2) and (6)
EPA Tier 4 generators with annual testing reports, § 455-19.1.E(7)(a)-(b)
E-waste plan for servers, batteries, and hazardous materials, § 455-19.1.L.
Energy usage plan; renewables only encouraged, § 455-19.1.E(5)
Substations at side or rear and screened; lines 34.5 kV and below buried, § 455-19.1.I(2)-(4)
Mechanical equipment screened on all sides, § 455-19.1.C
Architectural elevations required, § 455-19.1.D
Plan accepted by fire department, radio coverage, 24-hour signage; no annual update, § 455-19.1.J
Construction plan with delivery times and routes; no bond, § 455-19.1.K
Plan and closure notice; security optional, § 455-19.1.M
One post-construction study, § 455-19.1.F(2)
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the PBO district
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data