City of Easton
Anti-Data Center Policies
Easton city formally opposes building or expanding data centers and urges city boards and commissions to follow that position, creating an obstacle to new projects. The resolution does not ban them or address existing facilities.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · City of EastonExpresses Easton City Council’s opposition to data center construction, development, or expansion within the city and urges boards and commissions to follow that position.Easton City Council resolution opposing data centers
What this means
The resolution formally opposes building, developing, or expanding data centers and encourages city boards and commissions to follow that position, creating a significant obstacle to new projects (opposes construction, development or expansion). It does not expressly ban data centers or address operating existing facilities, so its effect is less severe than an outright prohibition.
People behind it
- Mayor Salvatore J. Panto, Jr.
Introduced Resolution 165-2026 opposing data center development in Easton. The resolution was introduced by Mayor Salvatore J. Panto, Jr.
Restrictions & requirementsHide restrictions & requirements1
The resolution formally opposes the design, construction, development, or expansion of data centers within Easton and encourages boards and commissions with project-approval authority to follow that position; it does not establish an explicit ban.
Sources
pending · Easton CityVersion 3 of the draft (October 23, 2026), revised after the Lehigh Valley Planning Commission's October 16, 2026 review letter, is scheduled for review and a recommendation to City Council by the city Planning Commission on November 4, 2026, after which City Council must advertise and hold a public hearing before it can adopt the amendments, and no ordinance number has been assigned.Easton City, Northampton County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places, noise limits and sound testing and money set aside for eventual removal. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements36
Special exception by the Zoning Hearing Board; no lapse period for the approval, only the six-month zoning permit abandonment rule, § 595-05(D)
1,000 ft from the lot line of any existing dwelling and any lot in the WW, SS, DD, or CH districts, applied to the Data Center use, which by definition includes its mechanical, electrical, and cooling infrastructure, § 595-32(G)(4)(j) and § 595-09 G12
80 ft maximum inclusive of rooftop structures, below the 100 ft district limit for nonresidential uses, § 595-32(G)(4)(k) and §§ 595-22(D), 595-23(D)
Environmental impact assessment required, covering riparian buffers, streams, and wetlands as critical impact areas; no buffer width set, § 595-32(G)(4)(a) and § 520-40(B)(6)
Energy management plan states the phasing of electric load; no expansion approval trigger, § 595-32(G)(4)(d)
Single all-day limit of 55 dBA at any lot line, with a pure tone penalty of 5 dBA; no stated measurement standard, § 595-32(G)(4)(i)
Single all-day limit of 70 dBC, above the 60 dBC day and 55 dBC night standard, § 595-32(G)(4)(i)
Predictive study before construction and a post-construction study 1 to 12 months after the first certificate of occupancy, plus testing on complaint; no stated method or full-load condition for the post-construction study, § 595-32(G)(4)(i)
Generator testing must be evaluated in the sound study only; no testing hours or hours cap, § 595-32(G)(4)(i)
Certified water utilization report and proof of adequate public water capacity, with DRBC approval for withdrawals of 100,000 gpd or more; public water not required and no well study, § 595-32(G)(4)(b)
Cooling system type and efficiency must be disclosed in the water report; no low-water cooling requirement, § 595-32(G)(4)(b)
Projected average, peak, and seasonal water demand and drought assumptions disclosed; no metered reporting or drought plan, § 595-32(G)(4)(b)
Wastewater documentation identifying discharge volume, destination, and pretreatment, and proof of disposal capacity, for which sewer authority approval is sufficient but not required before the zoning permit, § 595-32(G)(4)(c)
Stormwater management plan required through the environmental impact assessment; no added treatment or containment for fuel and transformer areas, § 595-32(G)(4)(a) and § 520-40(B)(3)
Emissions sources identified in the environmental impact assessment only; no generator emission standard, § 520-40(B)(1)
Certified thermal impact mitigation plan on how waste heat is managed, dissipated, or reused; no modeled property line temperatures, § 595-32(G)(4)(h)
Electronic waste and decommissioning plan for servers, batteries, hazardous materials, and cooling equipment; no disposal contract, § 595-32(G)(4)(f)
Documentation from the electric provider certifying available capacity and that it will serve the Data Center, submitted with the zoning permit or land development application, § 595-32(G)(4) and (d)
Energy plan with peak and annual demand, phasing of load, and a power usage effectiveness analysis, plus an alternative energy feasibility narrative; no solar requirement or incentive, § 595-32(G)(4)(d) and (e)
Accessory utility services, including substations, must be fenced, screened, or obscured from view; no placement or line burial rule, § 595-32(H)(4)(a) and (c)
Battery type, quantity, and location documented in the emergency plan only; no setbacks or fire code compliance stated, § 595-32(G)(4)(g)
Anticipated utility upgrades and known impacts on electric rates must be disclosed; no cost or tariff terms or executed agreement, § 595-32(G)(4)(d)
Class C buffer next to residential uses, minimum 20 ft wide, with dead plants replaced, § 595-32(G)(4)(l) and § 520-32(A)(4)-(6)
Accessory utility service equipment must be fenced, screened, or obscured; other outdoor equipment not addressed, § 595-32(H)(4)(c)
Floor plans and elevations and a historic resources map required in the community impact assessment; no visual impact study, § 520-40(A)(2) and (7)
Certified emergency response plan required; no fire company review or annual update, § 595-32(G)(4)(g)
Emergency plan must address any necessary first responder training; no training delivery required, § 595-32(G)(4)(g)
Type, quantity, and location of battery, fuel, and hazardous materials must be documented; no storage setbacks or spill plan, § 595-32(G)(4)(g)
Annual Fire Department site inspection and safety plan recertification for on-site energy generation only; no report or correction period, § 595-32(H)(4)(a)
Traffic study required by peak-hour trip thresholds, with a full study above 150 trips, § 520-38.1(C)
Construction timing and financial security may be conditions of transportation approval; no construction hours, haul routes, or road bond required, § 520-38.1(U)(4)
Decommissioning plan without financial security, § 595-32(G)(4)(f)
Definition covers cryptocurrency mining, cloud computing, and training or deploying large language models; accessory data center defined without a size or power limit, § 595-09 G12 and I17
One post-construction sound study, with further testing on complaint or changed operations, § 595-32(G)(4)(i)
General permit revocation for false statements; no data center revocation grounds or hearing, § 595-05(I)
Applicant pays for impact assessments and City professionals if its authors are not qualified, and consultant review fees for transportation studies only, §§ 520-40(D) and 520-38.1(X)
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: special exception in the Adaptive Reuse and Expressway Transitional districts