East Rockhill Township
Anti-Data Center Policies
Bucks County’s Newtown-area ordinance allows data centers through an approval process but limits where and how they can operate, with setbacks, minimum site sizes, and noise controls.
Rating and summary from Bucks County as there are no scored current or future laws outside temporary restrictions for East Rockhill Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · East Rockhill TownshipThe supervisors tabled an earlier version on May 26, 2026, the county Planning Commission reviewed a revised amendment on September 2, 2026, and the revised amendment was advertised on October 1, 2026 for a hearing on October 27, 2026.East Rockhill Township, Bucks County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places and minimum site-size requirements. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements19
Conditional use; no expiration of approval, Art. III and H19
35-ft height limit; no rooftop equipment limit, H19.E
Separate site plan for each phase, H19.S
Single limits of 50 dBA next to residential and 62 dBA otherwise, H19.D(1)-(2)
Baseline study with application; later study only if conditioned, H19.D(3)-(4)
Water resource impact study if on-site water used, H19.J(6)
Must meet Air Pollution Control Act and federal NESHAP, H19.O(1)
Will-serve letter or capacity assessment with application; no inspection, H19.J(3)
On-site generation needs Fire Inspector approval and safety plan, H19.Q
Class 1 buffer with 6-ft berms; width not stated, H19.L
Fully shielded; 0.1 fc limit at residential lines, H19.N(2),(4)
Elevations and renderings of visible facades required, H19.G(6)
Safety plan approved by Fire Chief, recertified annually, H19.M(2)
Hazardous materials addressed only at decommissioning, H19.R
Annual Fire Chief site inspection, H19.M(2)
Second emergency access required, H19.M(1)
Security per estimate, not 110 percent; restoration within 12 months, H19.R
Quarterly noise studies only if conditioned, H19.D(4)
Township may draw on security and lien costs, H19.R(6)
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the I-1 and I-2 districts
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data