East Pikeland Township
Anti-Data Center Policies
East Pikeland Township requires data centers to meet setbacks from homes and other protected places and minimum site-size rules, increasing project costs while still allowing approval.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · East Pikeland TownshipThe current rules are in Ordinance No. 212, which the Board of Supervisors adopted on July 7, 2026.East Pikeland Township, Chester County — data-center ordinance (No. 212)
What this means
The measure imposes setbacks from homes or other protected places and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements22
Conditional use before the Board of Supervisors; no approval expiration, Section 1309.2
55 dBA day and 50 dBA night at residential property lines, Section 1713.2
Impulsive sound only, 20 dBA over ambient, Section 1713.2.A
Modeling with application and as-built study 6 months after occupancy; none at building permit, Section 1316.2.B(9)(b)
Vibration modeling and as-built study; general Section 1713 standard, Section 1316.2.B(9)(c)
Engineer water supply report; on-site groundwater barred for potable supply only, Section 1316.2.C(5)
Predicted usage study with will-serve letters, Section 1316.2.C(1)
Sewage disposal plan; cooling water meets state and federal standards, Section 1316.2.C(5)
State and federal emission rules with continuous monitoring; no Tier 4, Section 1316.2.B(9)(a)
Removal, disposal, and recycling of components at decommissioning, Section 1316.2.D(2)
Will-serve letters confirming capacity; no third-party electrical inspection, Section 1316.2.C(1).
Will-serve letters must identify required upgrades, Section 1316.2.C(1)
Berms of at least 30 ft with planting; buffer width under Section 1709, Section 1316.2.B(4)-(5)
Section 1711 lighting standards and glare limit, Section 1316.2.B(8)
Berms and planting screen the facility, Section 1316.2.B(5)
Site plan to emergency services and plan on request; no 24-hour contact, Section 1316.2.C(3)
Bulk tanks in containment; no storage setbacks, Section 1316.2.B(6)
Section 1316.2.C(6) requires a traffic impact analysis during the conditional use process under SALDO Section 306, addressing traffic safety and needed improvements, while construction road use is handled separately in Section 1316.2.C(2), and no study area is stated.
Construction traffic plan and road bond; no work hours, Section 1316.2.C(2)
Security of 110% of removal cost; 12-month removal, Section 1316.2.D
Section 1316.2.D(4) requires decommissioning estimates after the first year of operation and every fifth year, but Section 1316.2.D(5) only requires decommissioning funds to be posted and maintained and does not tie the security to each updated estimate.
Quarterly noise and vibration reports, Section 1316.5.C(3)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the U Utility District