East Pennsboro Township
Anti-Data Center Policies
East Pennsboro Township’s enacted ordinance sets cooling and water-use rules, noise limits and testing, and setbacks from homes and other protected places. Data centers remain eligible for approval, but must meet added requirements that increase costs.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · East Pennsboro TownshipThe current rules are in Ordinance No. 864-2026, which the Commissioners adopted on September 16, 2026.East Pennsboro Township, Cumberland County — data-center ordinance (No. 864-2026)
What this means
The measure imposes cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements30
Conditional use, § 514.2.C; no approval expiration
Agricultural lands are sensitive receptors with a 100-ft setback, but no bar on farmland, § 202 and § 804.Z.1.A
200 ft from water bodies, perennial streams, and wetlands, with an environmental impact statement; no added width on steep slopes, § 804.Z.1.A(6) and J(2)
Data center campus defined and planned as one integrated facility, § 202
Section 202 makes the Total Facility Electrical Load a condition of approval, Section 804.Z.1.K(4) states that the annual report does not authorize expansion beyond the approval, and Section 804.Z.1.P requires a tenant occupancy review, but no new approval is required for stated triggers such as added building area, generators, cooling, battery, or substation capacity, and like-for-like replacement is not exempted.
60 dBA day and 50 dBA night at the lot line, § 804.Z.1.D(1)
Section 804.Z.1.D(1) bars sound more than 10 dBA above pre-development or current ambient levels, measured with ANSI S1.4 meters under stated microphone and weather conditions, but the ambient is not an L90 measure and no floor is set below which the cap does not apply.
dBC limited to 15 dB above the dBA limits (75 dBC day, 65 dBC night), § 804.Z.1.D(1)
Section 804.Z.1.D(1)(a) to (c) require preliminary, interim, as-built, and annual sound studies using ANSI S1.4 meters, but the as-built study is not required at full operating load.
Testing only 8 a.m. to 5 p.m. on weekdays and no longer or more often than NFPA 110 requires, § 804.Z.1.F(9)
Vibration study showing none perceptible beyond the lot line, § 804.Z.1.D(3).
Water feasibility study for nonpublic sources; no bar on wells for cooling or pump tests, § 804.Z.1.E(3)
Section 804.Z.1.E(1) requires a closed-loop cooling system unless non-water-reliant technology is used, but it does not bar evaporative cooling or limit any evaporative system to a stated water-use rate shown to meet the noise limits.
Section 804.Z.1.E(6) requires a drought contingency plan implemented on a Commonwealth or Township drought declaration, and Section 804.Z.1.K requires an annual report of water demand and consumption to the Zoning Officer, but the reported use is not required to be metered.
Section 804.Z.1.E(5) requires the applicant to show that disposal of domestic and cooling or industrial wastewater has been provided and approved by the Sewage Enforcement Officer or PA DEP, but it does not state that the approval must be in hand before the zoning permit.
Tier IV generators required; no emissions testing, § 804.Z.1.F(8)
Decommissioning plan for equipment removal and recycling, with hazardous materials disposed of by law; no server recycling plan, § 804.Z.1.M
Electric provider certification of capacity; no electrical inspection, § 804.Z.1.F(2).
Engineer-certified energy usage plan and 10% renewable procurement above 50 MW; no required on-site renewables, § 804.Z.1.F(3)
Substations screened and placed to the side or rear; on-site lines of 34.5 kV and below buried, § 804.Z.1.F(4) to (6)
Known energy rate impacts must be noted; upgrade costs not assigned, § 804.Z.1.F(2)
25-ft planted landscape buffer, § 804.Z.1.B(6)
Equipment within 300 ft of roads, homes, or sensitive receptors enclosed or screened, and rooftop equipment screened on all sides for sound; equipment farther away not covered, § 804.Z.1.C and I(2)
Emergency response plan accepted by the fire department, with radio coverage and 24-hour contact signs, but no annual updates, § 804.Z.1.G and H
Plan must ensure first responders are trained; cost not assigned, § 804.Z.1.G(1)(e)
Annual fire safety inspections; no third-party electrical inspection, § 804.Z.1.G(1)(f)
Plan and security of at least 100% of cost, with completion within 18 months after decommissioning begins; not 110% or 6 months, § 804.Z.1.M
Annual sound studies and annual resource demand reports on power and water use, § 804.Z.1.D(5) and K
As-built noise violations are ordinance violations, with liens and injunctive relief for decommissioning, § 804.Z.1.D and M
New tenants must be identified in a tenant occupancy review before operating; end user not required before approval, § 804.Z.1.P
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the ANX Annex district
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data