East Marlborough Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for East Marlborough Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · East Marlborough Township
The Board of Supervisors listed a public hearing and possible adoption of Ordinance No. 02-2026 on its October 14, 2026 agenda, but the outcome has not been confirmed because October minutes are not yet posted.East Marlborough Township, Chester County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements30
  • LI Limited Industrial District only, Section 450-1002.B(16)

  • Conditional use; no approval expiration, Section 450-1003.J

  • 35 ft; no rooftop equipment height limit, Section 450-1003.J(4)

  • Environmental impact study required, Section 450-1003.J(14)(c)

  • Only later energy systems need an amended approval, Section 450-1003.J(13). Version 2.0 names generators and battery capacity as expansion triggers, so an amended approval for later energy systems meets part of the full standard and earns 1 point.

  • Section 450-1003.J(10)(a) sets 45 dBA day and 40 dBA night and weekend limits at the property line, measured with ANSI S1.4 Type 1 or Type 2 meters calibrated before and after each reading, with a 15-minute minimum per location (Table 3).

  • Section 450-1003.J(10)(b) and Table 4 treat an increase of more than 3 dBA above the baseline ambient level documented before construction as a violation, but the baseline is not defined as L90 and no floor is set below which the cap does not apply.

  • 60 dBC day and 50 dBC night, Section 450-1003.J(10)(a)

  • Pre-construction study and as-built study within 180 days; none at building permit, Section 450-1003.J(10)

  • Section 450-1003.J(11)(f) requires air-cooled or closed-loop water circulation systems and Section 450-1003.J(11)(e) bars groundwater and direct surface withdrawals for cooling, but evaporative systems are not expressly barred or limited to a stated water-use rate shown to meet the noise limits.

  • Section 450-1003.J(11)(a) and (d) require connection to metered public water and annual reports to the Township of the sources and volumes of water used, and Section 450-1003.J(11)(g) requires a drought response plan that addresses state, water supplier, and local drought declarations.

  • Tier 4 generators with annual testing reports, Section 450-1003.J(9)(g)(2)

  • Thermal impact mitigation plan including waste heat reuse, Section 450-1003.J(14)(d).

  • Electronic waste plan for servers, batteries, and hazardous materials, Section 450-1003.J(17).

  • Utility impact study and interconnection documents; no electrical inspection, Section 450-1003.J(8)-(9)

  • Energy usage plan; renewables documented, not required, Section 450-1003.J(9)(g)(1)

  • Substations to the side or rear and screened; all power lines buried, Section 450-1003.J(9)(b)-(d)

  • 100-ft buffer yard next to sensitive receptors and residential districts, Section 450-1003.J(7)(d).

  • Facade offsets and material and color limits, Section 450-1003.J(7)

  • Equipment screened on all sides; no height or acoustic standard, Section 450-1003.J(5)

  • Elevations and renderings required; no viewshed study, Section 450-1003.J(7)

  • Fire runoff containment; no storage setbacks, Section 450-1003.J(15)(k)

  • Annual fire safety inspections; no electrical inspection, Section 450-1003.J(15)(a)

  • Section 450-1003.J(14)(a) requires a traffic impact study in every case covering access, road capacity, and offsite flow on the Township network and surrounding areas, but it does not cover construction traffic and sets no study area reaching the nearest arterial or interchange.

  • Construction plan sets access times and locations; no road bond, Section 450-1003.J(16)

  • 150% security and closure notice; completion within 18 months, Section 450-1003.J(18)

  • Section 450-1003.J(18)(e)(iii) requires the decommissioning estimate to be updated annually, but Section 450-1003.J(18)(g) only requires the security balance to be reviewed annually and does not require it to be adjusted to match the updated estimate.

  • Annual water, load-shedding, and noise compliance reporting, Section 450-1003.J(11),(19),(21)

  • Section 450-1003.J(22)(d) allows the Board to revoke or suspend the conditional use approval after a public hearing and Section 450-1003.J(22)(b) enforces civil penalties under MPC Section 617.2, but no grounds for revocation are stated and MPC Section 616.1 is not cited.

  • Section 450-1003.J(21)(a) requires the applicant to fund a consultant escrow at the time of the conditional use application, which is review at the zoning stage rather than in land development review.

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the LI Limited Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data