East Hanover Township

Anti-Data Center Policies

East Hanover allows data centers by special exception in industrial areas, but requires at least 10-acre lots, extensive plans, and money set aside for eventual removal. These requirements may increase costs and delay approvals, but do not ban projects.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · East Hanover Township
Requires data centers in East Hanover Township to obtain special approval in industrial areas and meet rules for site size, screening, noise, water use, environmental impacts, energy, emergencies, cooling, and decommissioning.East Hanover Township data center zoning amendment

What this means

The measure would allow data centers as a special exception in industrial areas, but it adds meaningful approval and planning burdens: lots must be at least 10 acres and applicants must submit water, environmental, energy, emergency, and decommissioning plans. Those steps could add costs and delay projects, but they do not amount to a ban.

People behind it

  • Developed the ordinance to ensure data centers were addressed in zoning if a developer submitted a plan (“developed this ordinance”).

  • Voted unanimously to pass the zoning amendment (“voted unanimously to pass”).

Restrictions & requirementsHide restrictions & requirements10
  • Data centers are allowed in the industrial district only by special exception, requiring additional approval. The use is added as a special exception

  • A data center lot must be at least 10 acres. Lots to be at least 10 acres

  • Equipment must be fully enclosed where possible; where it cannot be enclosed, it must be fully screened. Fully enclose equipment

  • Data centers must comply with the nuisance ordinance’s ban on noise and vibration. The nuisance ordinance ban on noise and vibration

  • Applicants must analyze the facility’s water needs and document the water source. An analysis of water needs

  • Applicants must provide an environmental impact assessment and describe on-site processing operations and environmental impacts. An environmental impact assessment

  • Applicants must submit an energy management plan. Submit an energy management plan

  • Applicants must submit an emergency response plan. An emergency response plan

  • Applicants must provide a decommissioning plan and details about the proposed cooling method. A decommissioning plan

  • Industrial land next to residential or institutional land must have a buffer. A required buffer for industrial land adjacent to residential or institutional land

Benefits & exceptionsHide benefits & exceptions1
  • Data centers are allowed to seek approval as a special exception in the industrial district; this provides a defined siting path but does not guarantee approval. The ordinance adds the use as a special exception.

Sources

current law · East Hanover Township
The current rules are in Ordinance 2026-04, which the Supervisors adopted on August 31, 2026.East Hanover Township, Lebanon County — data-center ordinance (No. 2026-04)

What this means

The measure imposes money set aside for eventual removal and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements25
  • 75-ft setback from residential land only, § 250-131.D(1)

  • 75-ft setback from institutional land, § 250-131.D(1)

  • Environmental impact assessment required, § 250-253.9.F

  • General nuisance standard with no numeric limit, § 250-253.9.D

  • Water needs analysis and feasibility study for nonpublic sources, § 250-253.9.E

  • Section 250-253.9.J(2) requires the cooling method to be disclosed with the special exception application and requires water-cooled systems to be closed loop, but evaporative systems are not barred or limited to a stated water-use rate and shown to meet the noise limits.

  • Projected water quantity disclosed, § 250-253.9.E(1)

  • Section 250-253.9.E(4) requires the applicant to demonstrate that disposal of domestic, cooling, and industrial wastewater has been provided and approved by the Sewage Enforcement Officer or the Pennsylvania DEP, as a criterion of the special exception.

  • Stormwater plan under Chapter 172, § 250-253.9.F(2)

  • EPA Tier 4 with annual testing and reports, § 250-253.9.G

  • Electronic waste plan for servers, batteries, and hazardous material, § 250-253.9.J(4).

  • Utility capacity letter and interconnection agreement; no third-party inspection, § 250-253.9.G(2).

  • Energy management plan; solar only encouraged, § 250-253.9.G(1)

  • On-site generation is a separate use needing its own approval, § 250-253.9.G.

  • Accessory uses kept out of the front and screened; lines not buried, § 250-253.9.C and J(1)

  • 75-ft screened setback next to residential land, § 250-131.D

  • Equipment within 400 ft enclosed or screened; 8-ft fence, § 250-253.9.C

  • Plan reviewed by fire department, with radio coverage; no annual updates, § 250-253.9.H

  • Plan must ensure responder training, § 250-253.9.H(1)(e)

  • Spill containment for fuel; no storage setbacks, § 250-253.9.G and J(1)

  • Annual fire safety inspections, § 250-253.9.H(1)(f)

  • Second emergency access required, § 250-253.9.H(1)(c)

  • Plan, closure notice, and deadlines; no financial security, § 250-253.9.K

  • Annual equipment and emissions test reports, § 250-253.9.G

  • Section 250-253.9.K(5) causes loss of the license to operate when an ownership change is not reported 90 days ahead, but no notice or hearing precedes the loss and no other revocation procedure is stated.

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Special exception in the Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data