East Hanover Township

Anti-Data Center Policies

East Hanover Township’s enacted ordinance permits data centers but requires cooling and water-use controls, noise limits and sound testing, and setbacks from homes and other protected places, increasing building and compliance costs.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · East Hanover Township
The Board of Supervisors adopted Ordinance No. 2026-02 by a 5 to 0 vote on August 18, 2026, immediately after the public hearing.East Hanover Township, Dauphin County — data-center ordinance (No. 2026-02)

What this means

The measure imposes cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements30
  • Limited to the IC and IC-1 districts, § 602.A.73(1)

  • Rooftop equipment limited to 20 ft above the roof; no building height set, § 602.A.73(2)(a)

  • PNDI study and woodland disturbance limits, § 602.A.73(2)(t) and (w)

  • 55 dBA day and 45 dBA night at the property line, § 602.A.73(2)(m)

  • Section 602.A.73(2)(m) bars sound more than 10 dBA and 10 dBC above pre-development ambient, with fixed day and night maximums at the property line, but the ambient is not defined as L90, no method for measuring it is stated, and no floor is set below which the cap does not apply.

  • 65 dBC day and 55 dBC night, plus frequency analysis, § 602.A.73(2)(m)

  • Section 602.A.73(2)(m) requires preliminary (before preliminary approval), interim (building permit), and as-built studies six months after occupancy using ANSI S1.4-2014 meters and ANSI S1.11 frequency analysis, but compliance is shown under typical operating conditions and the as-built study is not required at full operating load.

  • Feasibility study and hydrogeologic study with pump tests for wells; wells not barred where public water exists, § 602.A.73(2)(l)

  • Closed-loop or other water-minimizing system; cooling type must be disclosed, § 602.A.73(2)(o)

  • Section 602.A.73(3) requires an Annual Operating Compliance Report on water use, but metering is left to the authority under Section 602.A.73(2)(q), and the drought plan in Section 602.A.73(2)(l) only reduces water use during drought without being tied to state, basin commission, or supplier drought declarations.

  • Section 602.A.73(2)(q) requires the applicant to demonstrate that disposal of domestic, cooling, and industrial wastewater has been provided for and approved by the Sewage Enforcement Officer, DEP, and the Township Municipal Authority, with a will-serve letter for public sewer, as part of the conditional use showing that precedes the zoning permit.

  • EPA Tier 4 diesel generators with annual testing reports, § 602.A.73(2)(p)

  • Removal of above-surface facilities only; no e-waste plan, § 602.A.73(2)(x)

  • Utility capacity verification before land development approval; no electrical inspection, § 602.A.73(2)(h).

  • Generators addressed; peak shaving and grid supply prohibited, § 602.A.73(2)(p)

  • Substations part of the use and screened by 12-ft barrier, § 602.A.73(2)(d) and (e)

  • Berm buffer yard with plantings next to homes; no width of 100 ft, § 602.A.73(2)(d)

  • Section 602.A.73(2)(c) requires road-visible principal facades to avoid undifferentiated walls through recesses, fenestration, or changes in material, pattern, texture, or color, bars smooth block, tilt-up, and prefabricated steel panels on visible walls, and caps metal and vinyl cladding at 50 percent, but it sets no articulation intervals and no color standard.

  • All equipment screened on all sides; ground equipment height not set, § 602.A.73(2)(d)

  • Sight line plan required with conditional use filing, § 602.A.73(2)(d)

  • ERP accepted by fire company, annual inspections, 24-hour signage; no radio coverage or annual updates, § 602.A.73(2)(j) and (s)

  • ERP must ensure first responders receive training; no funding, § 602.A.73(2)(j)

  • 100-ft storage setback and spill containment, § 602.A.73(2)(g).

  • Annual fire safety inspections; no third-party electrical inspection, § 602.A.73(2)(j)

  • Traffic study only when required by SALDO § 419, § 602.A.73(2)(k)

  • Construction traffic route plan only, § 602.A.73(2)(s)

  • Security of 100% of cost; no closure notice or removal deadline, § 602.A.73(2)(x)

  • Annual Operating Compliance Report on water, sound, and vibration, § 602.A.73(3)

  • Remediation of noise violations and injunctive relief only, § 602.A.73(2)(m) and (x)

  • Township engineer review; applicant pays only for violation studies, § 602.A.73(2)(m)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the IC and IC-1 districts