East Goshen Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for East Goshen Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · East Goshen TownshipWould require data centers in East Goshen’s light-industrial district to obtain conditional-use approval and meet new rules on siting, noise, water and energy use, safety, and eventual decommissioning.East Goshen Township Zoning Amendment Regulating Data Centers by Conditional Use (Draft)
What this means
The draft would allow data centers only through conditional-use approval in the I-1 district, with a 300-foot setback from residences and sensitive uses (setback requirement). Extensive studies and rules on noise, water, power, cooling fluids, and emergency planning would make approval and ongoing operation significantly harder (noise limits and compliance requirements).
People behind it
- East Goshen Township Planning Commission
The Township identifies the Commission as a body that reviews or drafts zoning ordinance amendments; the draft data-center amendment is listed on its page.
- East Goshen Township Board of Supervisors
Identified in the draft ordinance as the body that would enact and ordain the measure.
Restrictions & requirementsHide restrictions & requirements18
Data centers are allowed only in the I-1 Light Industrial District and require conditional-use approval, rather than being permitted as of right. Conditional use
All data-center and accessory uses must be at least 300 feet from residentially zoned districts and from sensitive-receptor property boundaries. Set back a minimum of 300 feet
Applicants must submit emergency-response plans for Fire Marshal review and approval, coordinate with local responders as applicable, and provide a liaison reachable 24/7. Emergency response plan
Conditional-use applications must include noise and vibration studies and qualified-professional analyses showing no perceptible heat beyond lot lines, radiation within applicable legal limits, adequate cooling with no negative regional impact, and no project-caused electrical interference or voltage fluctuations. Applicants must also document electric-service capacity and submit a pipeline-awareness study. Noise and vibration study
Cooling may not rely primarily on private groundwater wells or direct surface-water withdrawals if public water is available. Closed-loop cooling is required unless the municipal engineer accepts an alternative shown to use less water and energy and not increase specified fluid hazards; cooling fluids containing PFAS are prohibited. Closed-loop water circulation system
Applicants must provide water and wastewater analyses, document public-system capacity where used, and obtain required state and regional permits before approval. A drought-response plan is also required. No approvals shall be granted
Wastewater, cooling fluid, and other liquids generally may not be discharged to stormwater systems, surface water, soil, or groundwater. Exceptions are specified for authorized NPDES or industrial-waste discharges, de minimis untreated potable water, and precipitation that has not contacted cooling fluid. No wastewater, cooling fluid
For sites with at least 1,000 gallons of total cooling-fluid inventory or any cooling fluid other than untreated potable water, specified equipment must have secondary containment and leak detection. Loops of at least 1,000 gallons need isolation valves and automatic pump shutdown; unexplained makeup exceeding 5% of a loop’s design volume in 30 days must be investigated and reported within 10 days. Plans, release notifications, and annual inventory and testing reports are also required. 1,000 gallons or more
On-site energy-generation systems serving normal operations are treated as separate principal uses and need separate approvals under applicable rules. Data-center buildings must be located between such systems and residential districts or other sensitive receptors. On-site substations face location and screening requirements; substations near non-industrial zoning or sensitive receptors must be set back at least 300 feet from the property line. Separate principal use
On-site power lines of 34.5 kV or below must be buried. Applicants must agree to fund required or reasonably anticipated public-utility infrastructure upgrades unless certified documentation shows none are necessary or Pennsylvania law or regulation bars the cost allocation. 34.5 kV and below shall be buried
Diesel backup generators must meet EPA standards and be tested annually, with reports to the municipality. Fossil-fuel emergency generation is limited to outages and routine maintenance or readiness testing capped at 100 hours per year; routine tests are restricted to weekdays from 9 a.m. to 3 p.m. Generators may not be used for voluntary utility or PJM demand-response programs. Capped at 100 hours per year
Battery-storage systems must include engineered, impermeable containment sized for the maximum anticipated contaminated firefighting-water volume, with emergency procedures for containing and disposing of contaminated water and hazardous materials. Collection and containment system
Buildings and accessory structures must meet screening requirements and provide specified renderings. Principal-building facades must meet design rules for offsets, materials, colors, architectural features, and entrances; fencing may not use barbed or razor wire. Horizontal offset of at least ten feet
Data centers must meet the current USGBC LEED BD+C: Data Centers rating system or an equivalent standard approved by the municipal engineer. Current USGBC LEED
A decommissioning plan is required. Decommissioning must begin within one year after operations cease or abandonment is noticed, with a possible one-year extension if the owner is actively marketing the property for a compatible replacement use; completion is due within 18 months after that, subject to a possible good-cause extension. The plan requires removal of above-ground facilities, lawful hazardous-material disposal, and site restoration. Decommissioning shall begin within 1 year
Modular and phased facilities are subject to the same applicable data-center requirements, and existing, approved, proposed, and reasonably foreseeable modules and infrastructure on a lot or contiguous or commonly controlled lots are aggregated for thresholds and standards. Temporary modular installations are limited to specified short-term purposes and must be removed by the approval deadline; continued or expanded operations require data-center approval. Considered one development
Noise rules require pre-construction and post-construction studies, with the post-construction study due within 90 days after operations commence. Limits vary by receiving-land-use category and time; low-frequency noise and vibration are also regulated. If a study shows noncompliance, a corrective plan is due within 30 days of notice and remediation generally within 90 days; the Township may require further testing or interim mitigation. Post-construction noise and vibration study
For projects over 25 MW or pursuing the GRID/COA route, before applicable zoning, building, or land-disturbance permits the applicant must show it submitted required Commonwealth permit applications and, if applicable, is proceeding under a project-specific DEP Consent Order and Agreement. Final Commonwealth permits and approvals must be provided before occupancy. Over 25 MW
Benefits & exceptionsHide benefits & exceptions8
Data centers may seek conditional-use approval in the I-1 Light Industrial District; this is the district the measure identifies for them. Data Centers in accordance with
The measure expressly recognizes a broad range of accessory facilities—including substations, generators, water and wastewater facilities, cooling equipment, and security structures—on the same tract or adjacent parcels developed as a unified data-center project. Ancillary uses or structures
On-site energy-generation systems that supply a data center during normal operations are contemplated, including solar, wind, fossil fuel, fuel cells, and nuclear; they require separate principal-use approval and must meet applicable regulations. Any energy generation system
Modular, prefabricated, containerized, and phased facilities are expressly allowed, subject to the same applicable standards as other data centers. Modules and infrastructure on a site or contiguous or commonly controlled lots count cumulatively; temporary installations are limited to specified short-term purposes and approval dates. Data center facilities may employ modular
A closed-loop cooling system is the default, but an applicant may propose an alternative that uses less water and energy if the municipal engineer is satisfied and the alternative does not increase specified cooling-fluid hazards. PFAS-containing cooling fluids are prohibited. An applicant may propose an alternative cooling system
If a site is served entirely by public water, the municipal engineer may waive certain items in the required water-feasibility study upon written request. Several listed items remain non-waivable. may be waived by the municipal engineer
The required LEED BD+C: Data Centers standard may be met with an equivalent design standard, if the municipal engineer approves it. or equivalent design standard
Backup fossil-fuel generators may operate during emergency outages and for routine maintenance or readiness testing, capped at 100 hours per year; testing is limited to weekdays from 9 a.m. to 3 p.m. They may not be used for voluntary utility or PJM demand-response programs. When the primary source of energy is not available
Sources
pending · East Goshen TownshipThe Planning Commission sent the draft, revised September 24, 2026, to the Board of Supervisors and Chester County, and the county's October 23, 2026 review letter recommended further changes before the Board acts.East Goshen Township, Chester County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements24
Conditional use; no approval expiration, Section 240-31.C(3)
55 dBA day and 45 dBA night at residential property lines, [12] Table 2
Section [12], Table 6, treats an increase of 3 dBA or more above the baseline ambient level documented before construction as a violation, measured with a Type 1 or Type 2 ANSI meter, but the baseline is not defined as L90 and no floor is set below which the cap does not apply.
60 dBC day and 50 dBC night, [12] Table 3
Pre-construction study and as-built study within 90 days; none at building permit, [12]
Section [12][c][vi] limits vibration to 65 VdB measured under ISO 2631-1, 72 VdB at the nearest residential receptor under ISO 2631-2 and FTA methods, and building damage levels measured under USBM RI 8507, with pre-construction and post-construction vibration studies.
Closed-loop required, but evaporative cooling towers are contemplated, [9][b] and [h][vi]
Projected water needs and drought response plan; no water use reporting, [9]
Generators must meet EPA emission standards, with annual testing; no Tier 4, [8]
Decommissioning disposal or recycling of materials and hazardous materials, [5][g]
Utility certification of capacity; no electrical inspection, [5][d].
LEED design standard only; no energy usage plan, [6]
On-site generation is a separate principal use with its own approval, [7][a].
Substations to the side or rear and screened; lines of 34.5 kV or less buried, [7]
Firefighting water containment only; no NFPA 855, [7][g]
Section [7][f] requires the applicant to agree to fund any public utility infrastructure upgrades that may be required, and Section [5][d] requires a capacity certification noting known impacts on availability, but the required upgrades need not be identified or disclosed.
Facade offsets, material limits, and articulated entrances, [10].
Full screening under Section 240-27C(3), [4]
Renderings from roadways and residential areas; no historic site study, [4]
Plan approved by the Fire Marshal and a 24-hour emergency liaison; no annual updates or radio coverage, [2]-[3]
Cooling fluid secondary containment; no storage setbacks, [9][h]
Decommissioning plan without financial security, [5][g]
Annual cooling fluid inventory reports including make-up volumes, [9][h][viii]
Continuing condition of approval and interim curtailment; no specific penalties, [9][h][ix] and [12][h]
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the I-1 Light Industrial District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data