East Fallowfield Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for East Fallowfield Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · East Fallowfield Township
The Planning Commission sent a revised draft to the Board of Supervisors on October 5, 2026, and the Board's October 27, 2026 agenda listed authorizing advertisement of a draft dated October 23, 2026.East Fallowfield Township, Chester County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements26
  • 350-ft side setbacks from all property lines and 800-ft substation setback from residential parcels; rear yard not set, § 27-1735.1.C and 2.J(1)(d)

  • 50-ft buffer free of structures from any Sensitive Receptor, including schools, day care, hospitals, and parks, § 27-1735.2.A

  • 35 ft maximum; no rooftop equipment height limit, § 27-1735.1.D

  • Section 27-1735.2.G sets 40 dBA Leq (1-hour) for both the daytime and nighttime periods at residential property lines, and Section 27-1735.2.D(2), (3), and (6) require measurement at the property boundary nearest occupied buildings by a sealed professional engineer under standardized methodologies, including at peak cooling load.

  • 40 dBC day and night at residential property lines, § 27-1735.2.H

  • Study with the conditional use application and as-built studies after opening; none at building permit, § 27-1735.2.C-D

  • Section 27-1735.2.D(7) limits vibration to 65 VdB measured in accordance with ISO 2631-1, and Section 27-1735.2.C and D require pre-construction and post-construction vibration studies.

  • Public water required and no groundwater within 2,000 ft for cooling; no hydrogeologic study with pump tests, § 27-1735.2.H(1)

  • Air-cooled or closed-loop cooling required; alternatives only if they use less water and energy, § 27-1735.2.H(1)(e).

  • Daily and annual use estimates and drought response plan; no cap or ongoing reporting, § 27-1735.2.H(1)(b) and (f)

  • Reserve parking counted as impervious coverage for stormwater planning and no untreated discharge to stormwater systems; no other stormwater standards, § 27-1735.2.H(2)(3) and N

  • Diesel generators must meet EPA Tier 4, with annual testing reports, § 27-1735.2.I(2)(a)-(b)

  • Compliance with applicable rules for off-site waste and e-waste disposal; no e-waste plan, § 27-1735.2

  • Utility interconnection application, transmission security agreement, and energization date required; no electrical inspection, § 27-1735.2.I(1)(f)

  • Energy usage plan with documented renewable efforts; no on-site renewable requirement, § 27-1735.2.I(1)

  • Power generation systems are separate uses with their own approvals, § 27-1735.2.J(1).

  • Substations to the side or rear and screened; on-site lines of 34.5 kV and below buried, § 27-1735.2.J(1)(a)-(c)

  • 50-ft planted buffer next to residential districts and Sensitive Receptors, § 27-1735.2.A

  • Cooling and generator equipment fully enclosed or treated to meet noise limits; no height standard for ground equipment, § 27-1735.2.A

  • Architectural building elevations required; no visual impact study, § 27-1735.2.B

  • Emergency Response Plan accepted by the fire department; no annual updates, radio coverage, or 24-hour contacts, § 27-1735.2.K(1)

  • Annual fire safety inspections; no third-party electrical inspection, § 27-1735.2.K(1)(e)

  • Construction plan sets times and locations for construction access; no road damage bond, § 27-1735.2.L

  • 110% financial security and completion within 12 months; no closure notice, § 27-1735.2.M

  • Security amount updated every three years; no update after the first year, § 27-1735.2.M

  • Sound and vibration studies within 90 days of opening and annually thereafter, plus annual generator reports, § 27-1735.2.D(1) and I(2)(b)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the O-I Office/Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data